May 13, 2026
Resseguie Street, 16th Street to 9th Street
PROJECT WORK:
- Mainline pipe work is complete on Resseguie Street.
- Sidewalk and roadway improvements will resume on June 1st.
UTILITY WORK:
- Veolia’s work is complete.
- Intermountain Gas will continue relocating the gas line between 15th Street and 16th Street, beginning May 4th.
Fort Street, 16th Street to 15th Street
PROJECT WORK:
- Mainline pipe work is complete on Fort Street.
- Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK:
- Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
Share May 13, 2026 on Facebook
Share May 13, 2026 on X (formerly Twitter)
Share May 13, 2026 on Linkedin
Email May 13, 2026 link
This project is substantially complete.