May 21, 2026
Resseguie Street, 16th Street to 9th Street
PROJECT WORK: Intermountain Gas will complete work between 15th and 16th by next Friday, May 29th. ACHD's Contractor will start work on June 1 in the following areas:
Resseguie, 13th to 16th. 14th and 15th will be closed; 13th and 16th will remain open.
Fort, 15th to 16th
15th , Fort to Resseguie
Intermountain Gas will be starting work on June 1 on Resseguie, 9th to 11th. 10th Street will be closed; 9th Street and 11th Street will remain open.
UTILITY WORK: Veolia’s work is complete.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume on June 1st.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume on June 1st.