November 20, 2025

  • Resseguie Street, 16th Street to 9th Street
  • PROJECT WORK: Resseguie Street will be closed from 13th Street to 15th Street on November 18th – November 26th for pipe replacement work.
  • Work is weather dependent. Sidewalk and roadway improvements will resume in the spring.
  • UTILITY WORK: Veolia’s work is complete. Intermountain Gas will lower the gas line in the spring of 2026. Fort Street, 16th Street to 15th Street
  • PROJECT WORK: Fort Street will be closed from 16th Street to 15th Street on December 1st – December 5th for pipe replacement work. Sidewalk and roadway improvements will resume in the spring.
  • UTILITY WORK: Veolia’s work is complete. 15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.