September 3, 2026
Resseguie Street, 16th Street to 9th Street
PROJECT WORK: Resseguie, 9th Street to 11th Street and 13th Street to 16th Street is substantially complete. Sidewalk and roadway improvements between 11th Street and 12th Street are on-going. Resseguie is closed during the work. Paving is anticipated for the week of September 14th.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas’ work is complete.
Fort Street, 16th Street to 15th Street - Substantially complete.
15th Street, Fort Street to Resseguie Street - Substantially complete.