Phillippi Street | Malad Street
The Ada County Highway District is making plans to improve walking and bicycling routes on streets in your neighborhood. These projects will make it easier for neighbors to access schools, jobs, shopping and public transportation.
Street Segments
- Phillippi Street, Irving Street to Overland Road
- Malad Street, Phillippi Street to Orchard Street
Project Features
- Reconstructing Philippi St. and narrowing travel lanes
- Adding sidewalks, bulb-outs and pedestrian ramps
- Reconfiguring intersection at Philippi/ Overland to include pedestrian signal and medians to prevent cut-thru traffic.
- Adding pedestrian signals and crossings at Philippi /Emerald and Malad /Orchard intersections.
- Placing sharrows and wayfinding signs
- Adjusting on-street parking
The Ada County Highway District is making plans to improve walking and bicycling routes on streets in your neighborhood. These projects will make it easier for neighbors to access schools, jobs, shopping and public transportation.
Street Segments
- Phillippi Street, Irving Street to Overland Road
- Malad Street, Phillippi Street to Orchard Street
Project Features
- Reconstructing Philippi St. and narrowing travel lanes
- Adding sidewalks, bulb-outs and pedestrian ramps
- Reconfiguring intersection at Philippi/ Overland to include pedestrian signal and medians to prevent cut-thru traffic.
- Adding pedestrian signals and crossings at Philippi /Emerald and Malad /Orchard intersections.
- Placing sharrows and wayfinding signs
- Adjusting on-street parking
-
Final Design
Share Final Design on Facebook Share Final Design on X (formerly Twitter) Share Final Design on Linkedin Email Final Design linkThe final design for the Phillippi Street | Malad Street Project is complete. We made a few updates based on technical review and feedback from neighbors.
What changed
- Adding bicycle push buttons at the Phillippi and Overland intersection, and Malad and Orchard intersection.
- Adding permeable pavers to the on-street parking areas to help manage stormwater.
- Phillippi St, Cassia St to Anna St
- Will include 5 foot sidewalks on the west and 5-6 foot sidewalks on the east instead of 7-foot sidewalks on both sides.
- Adding on-street parking on the west side between Cassia St and Grover St.
- During the public outreach we learned that on-street parking was important to neighbors. This change makes room for on-street parking on one side of the street while minimizing impacts to irrigation facilities, vegetation and landscaping.
- Phillippi St, Franklin Rd to Emerald St will have 5 foot sidewalk on both sides of the street instead of a mix of 5 and 10 foot sidewalk. This approach helps minimize impacts to commercial driveway access and better accommodates larger turning movements for commercial vehicles. It also provides a more consistent corridor design while better accommodating drainage.
View the updated designs under "Final Design Updates 2026".
Next Steps
Construction is currently scheduled to start in Fall 2029. In order to better coordinate with the significant utility relocations construction will be broken up into phases and spread out over a few years, wrapping up in 2033. However, this is a preliminary schedule that we will refine as we get closer to construction.
The final design for the Phillippi Street | Malad Street Project is complete. We made a few updates based on technical review and feedback from neighbors.
What changed
- Adding bicycle push buttons at the Phillippi and Overland intersection, and Malad and Orchard intersection.
- Adding permeable pavers to the on-street parking areas to help manage stormwater.
- Phillippi St, Cassia St to Anna St
- Will include 5 foot sidewalks on the west and 5-6 foot sidewalks on the east instead of 7-foot sidewalks on both sides.
- Adding on-street parking on the west side between Cassia St and Grover St.
- During the public outreach we learned that on-street parking was important to neighbors. This change makes room for on-street parking on one side of the street while minimizing impacts to irrigation facilities, vegetation and landscaping.
- Phillippi St, Franklin Rd to Emerald St will have 5 foot sidewalk on both sides of the street instead of a mix of 5 and 10 foot sidewalk. This approach helps minimize impacts to commercial driveway access and better accommodates larger turning movements for commercial vehicles. It also provides a more consistent corridor design while better accommodating drainage.
View the updated designs under "Final Design Updates 2026".
Next Steps
Construction is currently scheduled to start in Fall 2029. In order to better coordinate with the significant utility relocations construction will be broken up into phases and spread out over a few years, wrapping up in 2033. However, this is a preliminary schedule that we will refine as we get closer to construction.
-
Thank you
Share Thank you on Facebook Share Thank you on X (formerly Twitter) Share Thank you on Linkedin Email Thank you linkThank you to everyone who reviewed the design plans for Phillippi Street and Malad Street—or joined us at the public open house at the Library at Hillcrest in March!
Nearly 500 people participated in our online and in-person public meeting this spring and we appreciate the many thoughtful comments shared by the community. Take a quick look at the key themes we heard from neighbors.
What’s next?
In the coming months, the project team will continue environmental work and begin preliminary design. Your feedback will help guide these efforts.ACHD will share final design plans with the community next year.
Thank you to everyone who reviewed the design plans for Phillippi Street and Malad Street—or joined us at the public open house at the Library at Hillcrest in March!
Nearly 500 people participated in our online and in-person public meeting this spring and we appreciate the many thoughtful comments shared by the community. Take a quick look at the key themes we heard from neighbors.
What’s next?
In the coming months, the project team will continue environmental work and begin preliminary design. Your feedback will help guide these efforts.ACHD will share final design plans with the community next year.
-
Learn about changes coming to Phillippi and Malad streets
Share Learn about changes coming to Phillippi and Malad streets on Facebook Share Learn about changes coming to Phillippi and Malad streets on X (formerly Twitter) Share Learn about changes coming to Phillippi and Malad streets on Linkedin Email Learn about changes coming to Phillippi and Malad streets linkThere are two ways to learn about upcoming changes to Phillippi and Malad streets.
Join us for a public involvement meeting
-
WHEN:
- March 4, 2025 | 4-7 p.m.
-
WHERE:
- Library! at Hillcrest
- 5246 W Overland Rd., Boise
- The meeting will be an open house with no formal presentation.
View the designs and take the survey
While your comments are always welcome, the survey closed on March 11, 2025.
There are two ways to learn about upcoming changes to Phillippi and Malad streets.
Join us for a public involvement meeting
-
WHEN:
- March 4, 2025 | 4-7 p.m.
-
WHERE:
- Library! at Hillcrest
- 5246 W Overland Rd., Boise
- The meeting will be an open house with no formal presentation.
View the designs and take the survey
While your comments are always welcome, the survey closed on March 11, 2025.
-
WHEN:
View the final designs below.
-
March 04 2025
-
Sr. Project Manager
Phone 208-387-6100 Email connect@achdidaho.org -
Federal Aid Project Management Supervisor | ROW & Project Management
Phone 208-387-6100 Email connect@achdidaho.org