April 21, 2023

  • Utility work ongoing. Waiting on Idaho Power.
  • Grade work for the basin is nearly complete.
  • Wingwalls placed, placing aprons and cut off walls by April 21st.
  • Veolia starting water line.
Share April 21, 2023 on Facebook Share April 21, 2023 on X (formerly Twitter) Share April 21, 2023 on Linkedin Email April 21, 2023 link

This project is substantially complete