April 21, 2023

  • Utility work ongoing. Waiting on Idaho Power.
  • Grade work for the basin is nearly complete.
  • Wingwalls placed, placing aprons and cut off walls by April 21st.
  • Veolia starting water line.
Share April 21, 2023 on Facebook Share April 21, 2023 on Twitter Share April 21, 2023 on Linkedin Email April 21, 2023 link

This project is substantially complete