May 5, 2023

  • Grade work for the basin is nearly complete
  • Structure complete
  • Grade work started May 1st
  • Concrete cap installed
  • Sidewalk and gutter ongoing
  • Veolia water line ongoing
Share May 5, 2023 on Facebook Share May 5, 2023 on Twitter Share May 5, 2023 on Linkedin Email May 5, 2023 link

This project is substantially complete