- Contractor continues to pre sub base for the road.
- Work continues on the curb, gutter and sidewalk.
- The contractor anticipates paving the first week of June.
- Minor grading work continues on the basin.
Share June 2, 2023 on Facebook
Share June 2, 2023 on X (formerly Twitter)
Share June 2, 2023 on Linkedin
Email June 2, 2023 link
This project is substantially complete