  • Contractor continues to pre sub base for the road.
  • Work continues on the curb, gutter and sidewalk.
  • The contractor anticipates paving the first week of June.
  • Minor grading work continues on the basin.
Share June 2, 2023 on Facebook Share June 2, 2023 on X (formerly Twitter) Share June 2, 2023 on Linkedin Email June 2, 2023 link

This project is substantially complete