- Contractor scheduled to pave June 23rd.
- Water line tie-in complete for the basin.
- Minor grading work continues on the basin. Topsoil needed.
- Fence install around the basin started.
Share June 23, 2023 on Facebook
Share June 23, 2023 on Twitter
Share June 23, 2023 on Linkedin
Email June 23, 2023 link
This project is substantially complete