June 30, 2023
- Paving complete.
- Water line tie-in complete for the basin.
- Fence installation around the basin continues.
- Roadway open to traffic. Minor concrete repairs needed prior to pedestrian access.
- Basin dirt work ongoing - seeding will be in the fall.