  • Contractor continues to prep sub base for road.
  • Work continues on curb, gutter and sidewalk.
  • The contractor anticipates paving after the water hot tap. Likely middle/end of June.
  • Minor grading work continues on the basin. Top soil needed.
Share June 16, 2023 on Facebook Share June 16, 2023 on X (formerly Twitter) Share June 16, 2023 on Linkedin Email June 16, 2023 link

This project is substantially complete