March 10, 2023

  • Contractor has removed the majority of the trees.
  • Utility work ongoing.
  • Contractor closed Reutzel on March 6th.
  • Grade work for the basin is nearly complete. Contractor needs topsoil.
  • North and south foundation formwork complete. Concrete placed March 6th.
Share March 10, 2023 on Facebook Share March 10, 2023 on Twitter Share March 10, 2023 on Linkedin Email March 10, 2023 link

This project is substantially complete