March 24, 2023

  • Utility work ongoing.
  • Contractor closed Reutzel on March 6th.
  • Grade work for the basin is nearly complete.
  • North and south foundation form work complete.
  • Placement of box culvert scheduled for early April.
Share March 24, 2023 on Facebook Share March 24, 2023 on Twitter Share March 24, 2023 on Linkedin Email March 24, 2023 link

This project is substantially complete