March 31, 2023
- Utility work ongoing. Waiting on Idaho Power.
- Grade work for the basin is nearly complete.
- North and south foundation form work complete.
- Placement of box culvert scheduled for early-mid April.
Share March 31, 2023 on Facebook
Share March 31, 2023 on Twitter
Share March 31, 2023 on Linkedin
Email March 31, 2023 link
This project is substantially complete