May 26, 2023

  • Contractor continues to prep for sub-base for the road.
  • Work continues on curb, gutter and sidewalk.
  • The contractor anticipates paving the first week of June.
  • Minor grading work continues on basin.
Share May 26, 2023 on Facebook Share May 26, 2023 on X (formerly Twitter) Share May 26, 2023 on Linkedin Email May 26, 2023 link

This project is substantially complete