Beacon Light, Ballantyne to HWY 16

Share Beacon Light, Ballantyne to HWY 16 on Facebook Share Beacon Light, Ballantyne to HWY 16 on Twitter Share Beacon Light, Ballantyne to HWY 16 on Linkedin Email Beacon Light, Ballantyne to HWY 16 link

This project is substantially complete

Roadway and ADA Improvements (2023), Part 2

This fall, the Ada County Highway District will begin work on Beacon Light Road between Highway 16 and Ballantyne Lane. This pavement maintenance project consists primarily of removing and replacing the existing asphalt pavement. Work also includes reconstructing existing adjacent curb ramps to meet modern standards and stormwater pipe replacements. Construction is anticipated to end early summer of 2023.


Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

Roadway and ADA Improvements (2023), Part 2

This fall, the Ada County Highway District will begin work on Beacon Light Road between Highway 16 and Ballantyne Lane. This pavement maintenance project consists primarily of removing and replacing the existing asphalt pavement. Work also includes reconstructing existing adjacent curb ramps to meet modern standards and stormwater pipe replacements. Construction is anticipated to end early summer of 2023.


Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

This project is substantially complete

  • March 17, 2023

    Share March 17, 2023 on Facebook Share March 17, 2023 on Twitter Share March 17, 2023 on Linkedin Email March 17, 2023 link
    • Pipe work is complete.
    • Roadway work will be one in April or May.
  • March 10, 2023

    Share March 10, 2023 on Facebook Share March 10, 2023 on Twitter Share March 10, 2023 on Linkedin Email March 10, 2023 link
    • Pipe work is complete.
    • Road work will be completed in April or May.
  • March 3, 2023

    Share March 3, 2023 on Facebook Share March 3, 2023 on Twitter Share March 3, 2023 on Linkedin Email March 3, 2023 link
    • Beacon Light between Meridian Road and Ballantyne Lane will be closed March 6-10.
    • Roadway work will be done in April or May.
  • February 24, 2023

    Share February 24, 2023 on Facebook Share February 24, 2023 on Twitter Share February 24, 2023 on Linkedin Email February 24, 2023 link
    • Updated closure information starting March 3rd for one week.
    • Beacon Light will be closed from Meridian to Ballantyne for construction work.

  • February 17, 2023

    Share February 17, 2023 on Facebook Share February 17, 2023 on Twitter Share February 17, 2023 on Linkedin Email February 17, 2023 link
    • Pipe work ongoing.
    • Beacon Light Road between Park Lane and Meridian Road will be closed February 22 - March 1.
    • Beacon Light Road between Meridian Road and Ballantyne Lane will be closed march 1 - March 8.

  • February 10, 2023

    Share February 10, 2023 on Facebook Share February 10, 2023 on Twitter Share February 10, 2023 on Linkedin Email February 10, 2023 link
    • Pipe work is ongoing - weather dependent.
  • February 3, 2023

    Share February 3, 2023 on Facebook Share February 3, 2023 on Twitter Share February 3, 2023 on Linkedin Email February 3, 2023 link
    • Pipe work continues weather dependent.
  • January 27, 2023

    Share January 27, 2023 on Facebook Share January 27, 2023 on Twitter Share January 27, 2023 on Linkedin Email January 27, 2023 link
    • Beacon Light will be closed between Linder Road and Park Lane February 2 - 9
  • January 20, 2023

    Share January 20, 2023 on Facebook Share January 20, 2023 on Twitter Share January 20, 2023 on Linkedin Email January 20, 2023 link
    • Pipe work is ongoing.
    • Beacon Light will be closed between Lanewood and Palmer - January 18-25th.
  • January 17- Update to Closure Starting Date

    Share January 17- Update to Closure Starting Date on Facebook Share January 17- Update to Closure Starting Date on Twitter Share January 17- Update to Closure Starting Date on Linkedin Email January 17- Update to Closure Starting Date link
    supporting image

    The road closure between Lanewood Road and Palmer Lane is now expected to begin Thursday, January 19. Work is still expected to wrap up January 25, however, all work is weather dependent.