Beacon Light, Ballantyne to HWY 16

Share on Facebook Share on Twitter Share on Linkedin Email this link

This project is substantially complete

Roadway and ADA Improvements (2023), Part 2

This fall, the Ada County Highway District will begin work on Beacon Light Road between Highway 16 and Ballantyne Lane. This pavement maintenance project consists primarily of removing and replacing the existing asphalt pavement. Work also includes reconstructing existing adjacent curb ramps to meet modern standards and stormwater pipe replacements. Construction is anticipated to end early summer of 2023.


Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

Roadway and ADA Improvements (2023), Part 2

This fall, the Ada County Highway District will begin work on Beacon Light Road between Highway 16 and Ballantyne Lane. This pavement maintenance project consists primarily of removing and replacing the existing asphalt pavement. Work also includes reconstructing existing adjacent curb ramps to meet modern standards and stormwater pipe replacements. Construction is anticipated to end early summer of 2023.


Commuters are reminded to obey all road closure signs and follow the signs along the detour route. Commuters should never attempt to drive, bike, or walk on closed portions of the road, regardless of whether there appears to be active construction. It is unlawful to move or manipulate construction signs and doing so can put commuters and construction workers at great risk.

This project is substantially complete

  • June 16, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Mainline asphalt paving is complete. Minor work remains, including approach paving, manhole adjustments, and permanent striping.
  • June 2, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Asphalt paving resumed May 25th and will continue into early June. The roadway will remain open during construction. However, drivers should expect delays and consider alternative routes.
  • May 26, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Milling started May 1st and is now complete.
    • Asphalt paving resumed May 25th and will continue to early June. The roadway will remain open during construction. However, drivers should expect delays and consider alternative routes.
  • May 19, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Milling started May 1st and is complete.
    • Asphalt paving began May 15th. The roadway will remain open during construction, however, drivers should expect delays and consider alternate routes.
  • May 12, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Milling started May 1st and is complete.
    • Asphalt paving is scheduled to begin May 15th. The roadway will remain open during construction. However, drivers should expect delays and consider alternative routes.
  • May 5, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Milling is scheduled to begin May 1st. Asphalt paving is scheduled to begin May 8th. The roadway will remain open during construction. However, drivers should expect delays and consider alternate routes.
  • April 21, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Pipe work is complete.
    • Roadway work is scheduled to begin May 1st.
  • April 14, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Pipework is complete.
    • Roadway work is scheduled to begin May 1st.
  • March 31, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Pipe work is complete. Roadway work will be done in April or May.
  • March 24, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Pipe work is complete.
    • Roadway work will be done in April or May.