November 1, 2024
- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic. Bike lanes are closed as well.
- Base material import and grading is complete.
- Irrigation work complete.
- Light pole bases and electrical boxes are set.
- Curb and gutter being placed.
- Concrete island and various sidewalk/ped ramps have been placed.