Rose Hill and Owyhee Street Intersection
This project is substantially complete.
The Ada County Highway District (ACHD) will begin repair work in mid-July on the east leg of the Rose Hill and Owyhee roundabout to address a drainage issue. Construction is expected to last approximately one month.*
Why the fix?
Water has been pooling in this area due to outdated design standards, construction survey errors, and a lack of proper drainage when the roundabout was originally built.
What's the solution?
ACHD will install a seepage bed to improve stormwater drainage and prevent future pooling.
Construction Impacts
- The east leg of the intersection will be closed for the duration of the work
- Pedestrian detours and sidewalk closures
- General construction noise, dust, equipment backup alarms and ground vibration
- Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
- The contractor will work with property owners to minimize impacts
*Construction schedules may change.
The Ada County Highway District (ACHD) will begin repair work in mid-July on the east leg of the Rose Hill and Owyhee roundabout to address a drainage issue. Construction is expected to last approximately one month.*
Why the fix?
Water has been pooling in this area due to outdated design standards, construction survey errors, and a lack of proper drainage when the roundabout was originally built.
What's the solution?
ACHD will install a seepage bed to improve stormwater drainage and prevent future pooling.
Construction Impacts
- The east leg of the intersection will be closed for the duration of the work
- Pedestrian detours and sidewalk closures
- General construction noise, dust, equipment backup alarms and ground vibration
- Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
- The contractor will work with property owners to minimize impacts
*Construction schedules may change.
This project is substantially complete.
-
June 13, 2025
Share June 13, 2025 on Facebook Share June 13, 2025 on Twitter Share June 13, 2025 on Linkedin Email June 13, 2025 linkACHD will begin repair work in mid-July on the east leg of the Rose Hill and Owyhee roundabout to address a drainage issue. Construction is expected to last approximately one month.
ACHD will begin repair work in mid-July on the east leg of the Rose Hill and Owyhee roundabout to address a drainage issue. Construction is expected to last approximately one month.
This project is substantially complete.
-
November 15, 2024
Share November 15, 2024 on Facebook Share November 15, 2024 on Twitter Share November 15, 2024 on Linkedin Email November 15, 2024 link- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic. Bike lanes are closed as well.
- Concrete placements complete.
- Block wall installation complete on three of the four corners.
- Additional bikeway signage and devices are to be added next week.
- Asphalt paving is on-going.
- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic. Bike lanes are closed as well.
- Concrete placements complete.
- Block wall installation complete on three of the four corners.
- Additional bikeway signage and devices are to be added next week.
- Asphalt paving is on-going.
This project is substantially complete.
-
November 7, 2024
Share November 7, 2024 on Facebook Share November 7, 2024 on Twitter Share November 7, 2024 on Linkedin Email November 7, 2024 link- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic. Bike lanes are closed as well.
- Various concrete placements on going.
- Block wall installation nearly complete on three of the four corners.
- Additional bikeway signage and devices are to be added next week.
- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic. Bike lanes are closed as well.
- Various concrete placements on going.
- Block wall installation nearly complete on three of the four corners.
- Additional bikeway signage and devices are to be added next week.
This project is substantially complete.
-
November 1, 2024
Share November 1, 2024 on Facebook Share November 1, 2024 on Twitter Share November 1, 2024 on Linkedin Email November 1, 2024 link- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic. Bike lanes are closed as well.
- Base material import and grading is complete.
- Irrigation work complete.
- Light pole bases and electrical boxes are set.
- Curb and gutter being placed.
- Concrete island and various sidewalk/ped ramps have been placed.
- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic. Bike lanes are closed as well.
- Base material import and grading is complete.
- Irrigation work complete.
- Light pole bases and electrical boxes are set.
- Curb and gutter being placed.
- Concrete island and various sidewalk/ped ramps have been placed.
This project is substantially complete.
-
October 24, 2024
Share October 24, 2024 on Facebook Share October 24, 2024 on Twitter Share October 24, 2024 on Linkedin Email October 24, 2024 link- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic. Bike lanes are closed as well.
- Base material import and grading is nearly complete.
- Irrigation work complete.
- Light pole bases and electrical boxes are being set.
- Curb and gutter being placed.
- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic. Bike lanes are closed as well.
- Base material import and grading is nearly complete.
- Irrigation work complete.
- Light pole bases and electrical boxes are being set.
- Curb and gutter being placed.
This project is substantially complete.
-
October 17, 2024
Share October 17, 2024 on Facebook Share October 17, 2024 on Twitter Share October 17, 2024 on Linkedin Email October 17, 2024 link- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic. Bike lanes are closed as well.
- Base material import and grading is nearly complete.
- Irrigation work complete.
- Light pole bases and electrical boxes are being set.
- Curb and gutter being placed.
Due to unforeseen delays in chip seal operations impacting the project the new target end date for construction completion is late November.
- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic. Bike lanes are closed as well.
- Base material import and grading is nearly complete.
- Irrigation work complete.
- Light pole bases and electrical boxes are being set.
- Curb and gutter being placed.
Due to unforeseen delays in chip seal operations impacting the project the new target end date for construction completion is late November.
This project is substantially complete.
-
October 10, 2024
Share October 10, 2024 on Facebook Share October 10, 2024 on Twitter Share October 10, 2024 on Linkedin Email October 10, 2024 link- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic.
- Bike Lanes are closed as well.
- Base material import and grading is nearly complete.
- Irrigation work complete.
- Light pole bases and electrical boxes are being set.
- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic.
- Bike Lanes are closed as well.
- Base material import and grading is nearly complete.
- Irrigation work complete.
- Light pole bases and electrical boxes are being set.
This project is substantially complete.
-
October 4, 2024
Share October 4, 2024 on Facebook Share October 4, 2024 on Twitter Share October 4, 2024 on Linkedin Email October 4, 2024 link- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic. Bike Lanes are closed as well.
- Thermoplastic and painted pavement markings complete east and west of the roundabout.
- Contractor is working on grading the road.
- Irrigation work ongoing.
- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic. Bike Lanes are closed as well.
- Thermoplastic and painted pavement markings complete east and west of the roundabout.
- Contractor is working on grading the road.
- Irrigation work ongoing.
This project is substantially complete.
-
September 26, 2024
Share September 26, 2024 on Facebook Share September 26, 2024 on Twitter Share September 26, 2024 on Linkedin Email September 26, 2024 link- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic.
- Thermoplastic and painted pavement markings complete east and west of the roundabout. Minor adjustments to be made.
- Contractor started importing fill.
- Irrigation work ongoing.
- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic.
- Thermoplastic and painted pavement markings complete east and west of the roundabout. Minor adjustments to be made.
- Contractor started importing fill.
- Irrigation work ongoing.
This project is substantially complete.
-
September 20, 2024
Share September 20, 2024 on Facebook Share September 20, 2024 on Twitter Share September 20, 2024 on Linkedin Email September 20, 2024 link- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic.
- Thermoplastic and painted pavement markings complete east and west of the roundabout. Minor adjustments to be made.
- Contractor started demo and excavation.
- Tree removal complete.
- Survey set for irrigation and concrete placements.
- Irrigation work starting this week.
- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic.
- Thermoplastic and painted pavement markings complete east and west of the roundabout. Minor adjustments to be made.
- Contractor started demo and excavation.
- Tree removal complete.
- Survey set for irrigation and concrete placements.
- Irrigation work starting this week.
This project is substantially complete.
Contact Us
Who's Listening
-
Construction Coordinator
Phone 208-387-6100 Email connect@achdidaho.org -
Sr. Project Manager
Phone 208-387-6100 Email connect@achdidaho.org
Public Outreach
Related projects
Archived Projects
Key Dates
-
October 27 2021
-
October 12 2022