November 15, 2024

  • Rose Hill and Owyhee intersection is closed for the duration of the project.
  • Pedestrian detour in place for school traffic. Bike lanes are closed as well.
  • Concrete placements complete.
  • Block wall installation complete on three of the four corners.
  • Additional bikeway signage and devices are to be added next week.
  • Asphalt paving is on-going.
Share November 15, 2024 on Facebook Share November 15, 2024 on Twitter Share November 15, 2024 on Linkedin Email November 15, 2024 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>