  • Rose Hill and Owyhee intersection is closed for the duration of the project.
  • Pedestrian detour in place for school traffic.
  • Bike Lanes are closed as well.
  • Base material import and grading is nearly complete.
  • Irrigation work complete.
  • Light pole bases and electrical boxes are being set.
Share October 10, 2024 on Facebook Share October 10, 2024 on Twitter Share October 10, 2024 on Linkedin Email October 10, 2024 link

This project is substantially complete. 