October 17, 2024

  • Rose Hill and Owyhee intersection is closed for the duration of the project.
  • Pedestrian detour in place for school traffic. Bike lanes are closed as well.
  • Base material import and grading is nearly complete.
  • Irrigation work complete.
  • Light pole bases and electrical boxes are being set.
  • Curb and gutter being placed.

Due to unforeseen delays in chip seal operations impacting the project the new target end date for construction completion is late November.

Share October 17, 2024 on Facebook Share October 17, 2024 on Twitter Share October 17, 2024 on Linkedin Email October 17, 2024 link

This project is substantially complete. 