September 13, 2024

  • Rose Hill and Owyhee intersection is closed for the duration of the project.
  • Pedestrian detour in place for school traffic.
  • Thermoplastic and painted pavement markings complete east and west of the roundabout.
  • Minor adjustments to be made.
  • Contractor to start demo and excavation this week.
  • Tree removal complete.
Share September 13, 2024 on Facebook Share September 13, 2024 on Twitter Share September 13, 2024 on Linkedin Email September 13, 2024 link

This project is substantially complete. 