September 20, 2024
- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic.
- Thermoplastic and painted pavement markings complete east and west of the roundabout. Minor adjustments to be made.
- Contractor started demo and excavation.
- Tree removal complete.
- Survey set for irrigation and concrete placements.
- Irrigation work starting this week.
Share September 20, 2024 on Facebook
Share September 20, 2024 on X (formerly Twitter)
Share September 20, 2024 on Linkedin
Email September 20, 2024 link
This project is substantially complete.