September 20, 2024

  • Rose Hill and Owyhee intersection is closed for the duration of the project.
  • Pedestrian detour in place for school traffic.
  • Thermoplastic and painted pavement markings complete east and west of the roundabout. Minor adjustments to be made.
  • Contractor started demo and excavation.
  • Tree removal complete.
  • Survey set for irrigation and concrete placements.
  • Irrigation work starting this week.