November 15, 2024
- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic. Bike lanes are closed as well.
- Concrete placements complete.
- Block wall installation complete on three of the four corners.
- Additional bikeway signage and devices are to be added next week.
- Asphalt paving is on-going.
Share November 15, 2024 on Facebook
Share November 15, 2024 on Twitter
Share November 15, 2024 on Linkedin
Email November 15, 2024 link
This project is substantially complete.