November 15, 2024

  • Rose Hill and Owyhee intersection is closed for the duration of the project.
  • Pedestrian detour in place for school traffic. Bike lanes are closed as well.
  • Concrete placements complete.
  • Block wall installation complete on three of the four corners.
  • Additional bikeway signage and devices are to be added next week.
  • Asphalt paving is on-going.
Share November 15, 2024 on Facebook Share November 15, 2024 on Twitter Share November 15, 2024 on Linkedin Email November 15, 2024 link

This project is substantially complete. 