Share November 15, 2024 on Facebook
Share November 15, 2024 on Linkedin
Email November 15, 2024 link
- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic. Bike lanes are closed as well.
- Concrete placements complete.
- Block wall installation complete on three of the four corners.
- Additional bikeway signage and devices are to be added next week.
- Asphalt paving is on-going.
Share November 7, 2024 on Facebook
Share November 7, 2024 on Linkedin
Email November 7, 2024 link
- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic.
- Bike lanes are closed as well.
- Various concrete placements on going.
- Block wall installation nearly complete on three of the four corners.
- Additional bikeway signage and devices are to be added next week.
Share November 1, 2024 on Facebook
Share November 1, 2024 on Linkedin
Email November 1, 2024 link
- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic. Bike lanes are closed as well.
- Base material import and grading is complete.
- Irrigation work complete.
- Light pole bases and electrical boxes are set.
- Curb and gutter being placed.
- Concrete island and various sidewalk/ped ramps have been placed.
Share October 24, 2024 on Facebook
Share October 24, 2024 on Linkedin
Email October 24, 2024 link
- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic. Bike lanes are closed as well.
- Base material import and grading is nearly complete.
- Irrigation work complete.
- Light pole bases and electrical boxes are being set.
- Curb and gutter being placed.
Share October 17, 2024 on Facebook
Share October 17, 2024 on Linkedin
Email October 17, 2024 link
- Rose Hill and Owyhee intersection is closed for the duration of the project.
- Pedestrian detour in place for school traffic. Bike lanes are closed as well.
- Base material import and grading is nearly complete.
- Irrigation work complete.
- Light pole bases and electrical boxes are being set.
- Curb and gutter being placed.
Share August 30, 2024 on Facebook
Share August 30, 2024 on Linkedin
Email August 30, 2024 link
- Veolia water work complete.
- Pedestrian detour in place for school traffic.
- Thermoplastic and painted pavement markings will be completed this week.
Share July 26, 2024 on Facebook
Share July 26, 2024 on Linkedin
Email July 26, 2024 link
- Rose Hill and Owyhee intersection is scheduled to be closed starting July 29th.
- Contractor will begin demo immediately following the closure.
Share July 19, 2024 on Facebook
Share July 19, 2024 on Linkedin
Email July 19, 2024 link
- Rose Hill and Owyhee intersection is scheduled to be closed starting July 29th.
- Contractor will begin demo immediately following the closure.
Share June 14, 2024 on Facebook
Share June 14, 2024 on Linkedin
Email June 14, 2024 link
- Preconstruction meeting was held June 12th.
- Notice to proceed is anticipated for July 8th.
Share June 7, 2024 on Facebook
Share June 7, 2024 on Linkedin
Email June 7, 2024 link
The preconstruction meeting is scheduled for June 12th.