Rose Hill St. Temporary Traffic Calming, Roosevelt St. to Vista Ave.

Share Rose Hill St. Temporary Traffic Calming, Roosevelt St. to Vista Ave. on Facebook Share Rose Hill St. Temporary Traffic Calming, Roosevelt St. to Vista Ave. on Twitter Share Rose Hill St. Temporary Traffic Calming, Roosevelt St. to Vista Ave. on Linkedin Email Rose Hill St. Temporary Traffic Calming, Roosevelt St. to Vista Ave. link


ACHD is designing temporary traffic calming features for Rose Hill Street from Roosevelt Street to Vista Avenue to enhance the safety for all users.

The concept design was created through a community outreach process and parking analysis and was adopted by the ACHD Commission in Fall 2022.

The project will provide a variety of traffic calming measures and enhanced bicycle infrastructure along Rose Hill Street.

Project Description

  • Add on-street bike lanes, separated by a painted buffer with a vertical element.
  • Remove the continuous center left-turn lane in most areas.
  • Retain parking on one side of the street, except between Latah and Owyhee streets, alternating sides of the street to provide shifts in the travel lanes.

* Design of the Rose Hill and Owyhee mini-roundabout was completed as a separate project.


ACHD is designing temporary traffic calming features for Rose Hill Street from Roosevelt Street to Vista Avenue to enhance the safety for all users.

The concept design was created through a community outreach process and parking analysis and was adopted by the ACHD Commission in Fall 2022.

The project will provide a variety of traffic calming measures and enhanced bicycle infrastructure along Rose Hill Street.

Project Description

  • Add on-street bike lanes, separated by a painted buffer with a vertical element.
  • Remove the continuous center left-turn lane in most areas.
  • Retain parking on one side of the street, except between Latah and Owyhee streets, alternating sides of the street to provide shifts in the travel lanes.

* Design of the Rose Hill and Owyhee mini-roundabout was completed as a separate project.

  • November 7, 2024

    Share November 7, 2024 on Facebook Share November 7, 2024 on Twitter Share November 7, 2024 on Linkedin Email November 7, 2024 link
    • Rose Hill and Owyhee intersection is closed for the duration of the project.
    • Pedestrian detour in place for school traffic.
    • Bike lanes are closed as well.
    • Various concrete placements on going.
    • Block wall installation nearly complete on three of the four corners.
    • Additional bikeway signage and devices are to be added next week.
  • November 1, 2024

    Share November 1, 2024 on Facebook Share November 1, 2024 on Twitter Share November 1, 2024 on Linkedin Email November 1, 2024 link
    • Rose Hill and Owyhee intersection is closed for the duration of the project.
    • Pedestrian detour in place for school traffic. Bike lanes are closed as well.
    • Base material import and grading is complete.
    • Irrigation work complete.
    • Light pole bases and electrical boxes are set.
    • Curb and gutter being placed.
    • Concrete island and various sidewalk/ped ramps have been placed.
  • October 24, 2024

    Share October 24, 2024 on Facebook Share October 24, 2024 on Twitter Share October 24, 2024 on Linkedin Email October 24, 2024 link
    • Rose Hill and Owyhee intersection is closed for the duration of the project.
    • Pedestrian detour in place for school traffic. Bike lanes are closed as well.
    • Base material import and grading is nearly complete.
    • Irrigation work complete.
    • Light pole bases and electrical boxes are being set.
    • Curb and gutter being placed.
  • October 17, 2024

    Share October 17, 2024 on Facebook Share October 17, 2024 on Twitter Share October 17, 2024 on Linkedin Email October 17, 2024 link
    • Rose Hill and Owyhee intersection is closed for the duration of the project.
    • Pedestrian detour in place for school traffic. Bike lanes are closed as well.
    • Base material import and grading is nearly complete.
    • Irrigation work complete.
    • Light pole bases and electrical boxes are being set.
    • Curb and gutter being placed.
  • August 30, 2024

    Share August 30, 2024 on Facebook Share August 30, 2024 on Twitter Share August 30, 2024 on Linkedin Email August 30, 2024 link
    • Veolia water work complete.
    • Pedestrian detour in place for school traffic.
    • Thermoplastic and painted pavement markings will be completed this week.
  • July 26, 2024

    Share July 26, 2024 on Facebook Share July 26, 2024 on Twitter Share July 26, 2024 on Linkedin Email July 26, 2024 link
    • Rose Hill and Owyhee intersection is scheduled to be closed starting July 29th.
    • Contractor will begin demo immediately following the closure.
  • July 19, 2024

    Share July 19, 2024 on Facebook Share July 19, 2024 on Twitter Share July 19, 2024 on Linkedin Email July 19, 2024 link
    • Rose Hill and Owyhee intersection is scheduled to be closed starting July 29th.
    • Contractor will begin demo immediately following the closure.
  • June 14, 2024

    Share June 14, 2024 on Facebook Share June 14, 2024 on Twitter Share June 14, 2024 on Linkedin Email June 14, 2024 link
    • Preconstruction meeting was held June 12th.
    • Notice to proceed is anticipated for July 8th.
  • June 7, 2024

    Share June 7, 2024 on Facebook Share June 7, 2024 on Twitter Share June 7, 2024 on Linkedin Email June 7, 2024 link

    The preconstruction meeting is scheduled for June 12th.

  • May 31, 2024

    Share May 31, 2024 on Facebook Share May 31, 2024 on Twitter Share May 31, 2024 on Linkedin Email May 31, 2024 link
    • Notice to proceed is anticipated for June.