November 7, 2024

  • Rose Hill and Owyhee intersection is closed for the duration of the project.
  • Pedestrian detour in place for school traffic.
  • Bike lanes are closed as well.
  • Various concrete placements on going.
  • Block wall installation nearly complete on three of the four corners.
  • Additional bikeway signage and devices are to be added next week.
Share November 7, 2024 on Facebook Share November 7, 2024 on Twitter Share November 7, 2024 on Linkedin Email November 7, 2024 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>