August 30, 2024

  • Floating Feather & Plummer - Work began August 8th. Contractor working on underground electrical components. Concrete work is on-going.
  • Pollard Lane & Pickett Creek - Complete. Pedestrian signal was activated August 15th.
Share August 30, 2024 on Facebook Share August 30, 2024 on Twitter Share August 30, 2024 on Linkedin Email August 30, 2024 link

This project is substantially complete. 