September 26, 2024

Floating Feather & Plummer - Work is complete. Waiting for power to activate pedestrian signal, anticipated for the week of October 14th.

Pollard Lane & Pickett Creek - Complete. Pedestrian signal was activated August 15th.

Share September 26, 2024 on Facebook Share September 26, 2024 on Twitter Share September 26, 2024 on Linkedin Email September 26, 2024 link

This project is substantially complete. 