This project is substantially complete. 

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace two separate culverts on Star Road south of McMillan Road, as early as the beginning of November 2023.* Construction is expected to be complete spring of 2024.

This bridge improvement project will include removing and replacing the two existing bridges over the Five Mile Drain and Five Mile Feeder.

*Construction schedules may change due to high demand for contractors, labor, and supplies.

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace two separate culverts on Star Road south of McMillan Road, as early as the beginning of November 2023.* Construction is expected to be complete spring of 2024.

This bridge improvement project will include removing and replacing the two existing bridges over the Five Mile Drain and Five Mile Feeder.

*Construction schedules may change due to high demand for contractors, labor, and supplies.

This project is substantially complete. 

  • February 16, 2024

    Share February 16, 2024 on Facebook Share February 16, 2024 on Twitter Share February 16, 2024 on Linkedin Email February 16, 2024 link
    • Star Road is closed for the duration of the project.
    • Dewatering set up.
    • Placing Walls on South Bridge.
    • Placing Footings on North Bridge.
  • February 9, 2024

    Share February 9, 2024 on Facebook Share February 9, 2024 on Twitter Share February 9, 2024 on Linkedin Email February 9, 2024 link
    • Star Road is closed for the duration of the project.
    • Intermountain Gas company welding pipe for boring - Complete.
    • Dewatering set up.
    • Digging for footings.
    • Excavation ongoing.
    • Placing Footing February 1st on South Bridge.
    • Placing base for North Bridge.
  • February 2, 2024

    Share February 2, 2024 on Facebook Share February 2, 2024 on Twitter Share February 2, 2024 on Linkedin Email February 2, 2024 link
    • Star Road is closed for the duration of the project.
    • Intermountain Gas company welding pipe for boring - Complete.
    • Dewatering set up.
    • Digging for footings.
    • Excavation ongoing.
    • Placing Footing 2/1 on South Bridge.
    • Placing base for North Bridge.
  • January 26, 2024

    Share January 26, 2024 on Facebook Share January 26, 2024 on Twitter Share January 26, 2024 on Linkedin Email January 26, 2024 link
    • Star Road is closed for the duration of the project.
    • Intermountain Gas company welding pipe for boring - Complete.
    • Dewatering set up.
    • Removed north bridge.
    • Digging for footings - Excavation ongoing.
  • January 19, 2024

    Share January 19, 2024 on Facebook Share January 19, 2024 on Twitter Share January 19, 2024 on Linkedin Email January 19, 2024 link
    • Star Road is closed for the duration of the project.
    • Intermountain Gas company welding pipe for boring - Complete.
    • Dewatering set up.
    • Removed north bridge.
    • Digging for footings.
  • January 12, 2024

    Share January 12, 2024 on Facebook Share January 12, 2024 on Twitter Share January 12, 2024 on Linkedin Email January 12, 2024 link
    • Star Road is closed for the duration of the project.
    • Intermountain Gas company welding pipe for boring - Complete.
    • Dewatering set up.
    • Removed N. Bridge
  • January 5, 2024

    Share January 5, 2024 on Facebook Share January 5, 2024 on Twitter Share January 5, 2024 on Linkedin Email January 5, 2024 link
    • Star Road is closed for the duration of the project.
    • Intermountain Gas company welding pipe for boring - Complete.
    • Lumen complete relocating lines.
    • KRC starting first week of January.
  • December 22, 2023

    Share December 22, 2023 on Facebook Share December 22, 2023 on Twitter Share December 22, 2023 on Linkedin Email December 22, 2023 link
    • Star Road is closed for the duration of the project.
    • Intermountain Gas company welding pipe for boring o Boring ongoing
    • Lumen complete relocating lines
    • KRC starting first week of January
  • December 15, 2023

    Share December 15, 2023 on Facebook Share December 15, 2023 on Twitter Share December 15, 2023 on Linkedin Email December 15, 2023 link
    • Star Road is closed for the duration of the project.
    • Intermountain Gas company welding pipe for boring - Boring Ongoing.
    • Lumen complete relocating lines.
    • Dewatering starting December 18th.
  • December 8, 2023

    Share December 8, 2023 on Facebook Share December 8, 2023 on Twitter Share December 8, 2023 on Linkedin Email December 8, 2023 link
    • Star Road is closed for the duration of the project.
    • Intermountain Gas company welding pipe for boring.
    • Boring Complete, placing utilities until December 15th.
    • Lumen relocating their utility.
    • Dewatering starting Dec 18th.