State and 21st Streets Pedestrian Crossing Project

Share State and 21st Streets Pedestrian Crossing Project on Facebook Share State and 21st Streets Pedestrian Crossing Project on Twitter Share State and 21st Streets Pedestrian Crossing Project on Linkedin Email State and 21st Streets Pedestrian Crossing Project link

Starting as early as March, the Ada County Highway District (ACHD) will begin construction on the State Street and 21st Street Pedestrian Crossing project. The purpose of this project is to improve safety and increase connectivity for pedestrians. Construction is expected to be complete late summer of 2025.*

Project Description

  • Install an enhanced pedestrian crossing at State Street and 21st Street
  • Improve pavement markings
  • Install bulb-outs and reconstruct adjacent pedestrian ramps to meet modern standards
  • Update streetlights for enhanced visibility and safety
  • Widen sidewalks on the north side of State Street, 21st Street, and Pleasanton Avenue to improve accessibility and functionality

Construction Impacts

  • Temporary road closures
  • Pedestrian detours and sidewalk closures
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners and businesses to minimize impacts

*Construction schedules may change.

Starting as early as March, the Ada County Highway District (ACHD) will begin construction on the State Street and 21st Street Pedestrian Crossing project. The purpose of this project is to improve safety and increase connectivity for pedestrians. Construction is expected to be complete late summer of 2025.*

Project Description

  • Install an enhanced pedestrian crossing at State Street and 21st Street
  • Improve pavement markings
  • Install bulb-outs and reconstruct adjacent pedestrian ramps to meet modern standards
  • Update streetlights for enhanced visibility and safety
  • Widen sidewalks on the north side of State Street, 21st Street, and Pleasanton Avenue to improve accessibility and functionality

Construction Impacts

  • Temporary road closures
  • Pedestrian detours and sidewalk closures
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners and businesses to minimize impacts

*Construction schedules may change.

  • May 23, 2025

    23 May 2025
    Share May 23, 2025 on Facebook Share May 23, 2025 on Twitter Share May 23, 2025 on Linkedin Email May 23, 2025 link
    • Switched to north side May 12th.
    • Removal of road and sidewalk.
    • Electrical work ongoing.
    • Underground work once removals are complete.
  • May 16, 2025

    16 May 2025
    Share May 16, 2025 on Facebook Share May 16, 2025 on Twitter Share May 16, 2025 on Linkedin Email May 16, 2025 link
    • Switched to North side May 12th.
    • Removal of road and sidewalk.
    • Electrical work ongoing.
    • Underground work once removals are complete.
  • May 8, 2025

    08 May 2025
    Share May 8, 2025 on Facebook Share May 8, 2025 on Twitter Share May 8, 2025 on Linkedin Email May 8, 2025 link
    • Contractor working on Pleasanton Ave and 21st St.
    • Placing base material.
    • Curb and gutter being placed.
    • Paving complete on south side.
    • Ped ramps ongoing.
    • Switching to north side May 12th.
  • May 2, 2025

    02 May 2025
    Share May 2, 2025 on Facebook Share May 2, 2025 on Twitter Share May 2, 2025 on Linkedin Email May 2, 2025 link
    • Contractor working on Pleasanton Ave and 21st St.
    • Placing base material.
    • Curb and gutter being placed.
    • Paving complete on south side.
    • Ped ramps ongoing.
  • April 25, 2025

    25 Apr 2025
    Share April 25, 2025 on Facebook Share April 25, 2025 on Twitter Share April 25, 2025 on Linkedin Email April 25, 2025 link
    • Notice to proceed was March 10th.
    • Contractor working on Pleasanton Ave and 21st St.
    • Placing base material.
    • Curb and gutter being placed.
    • Paving anticipated April 30th.
  • April 17, 2025

    17 Apr 2025
    Share April 17, 2025 on Facebook Share April 17, 2025 on Twitter Share April 17, 2025 on Linkedin Email April 17, 2025 link
    • Contractor working on Pleasanton Ave and 21st St.
    • Excavation ongoing.
    • Conduits ongoing.
    • Placing base material.
  • April 11, 2025

    11 Apr 2025
    Share April 11, 2025 on Facebook Share April 11, 2025 on Twitter Share April 11, 2025 on Linkedin Email April 11, 2025 link
    • Notice to proceed was March 10th.
    • Contractor working on Pleasanton Ave and 21st St.
    • Excavation ongoing. Conduits ongoing.
    • Storm drainpipe ongoing.
  • April 4, 2025

    04 Apr 2025
    Share April 4, 2025 on Facebook Share April 4, 2025 on Twitter Share April 4, 2025 on Linkedin Email April 4, 2025 link
    • Contractor working on Pleasanton Ave and 21st St.
    • Excavation ongoing.
    • Conduits ongoing.
    • Storm drain pipe ongoing.
  • March 28, 2025

    28 Mar 2025
    Share March 28, 2025 on Facebook Share March 28, 2025 on Twitter Share March 28, 2025 on Linkedin Email March 28, 2025 link
    • Will be working on Pleasanton Ave and 21st St.
    • Excavation ongoing.
    • Conduits being placed starting March 24th.
  • March 20, 2025

    20 Mar 2025
    Share March 20, 2025 on Facebook Share March 20, 2025 on Twitter Share March 20, 2025 on Linkedin Email March 20, 2025 link
    • Will be working on Pleasanton Ave and 21st St.
    • Removals ongoing.
    • Conduits being placed starting March 24th.