-
Share June 26, 2025 on Facebook
Share June 26, 2025 on X (formerly Twitter)
Share June 26, 2025 on Linkedin
Email June 26, 2025 link
- Work mostly complete.
- Pavement markings remaining.
- Work mostly complete.
- Pavement markings remaining.
This project is substantially complete.
-
Share June 20, 2025 on Facebook
Share June 20, 2025 on X (formerly Twitter)
Share June 20, 2025 on Linkedin
Email June 20, 2025 link
- Switched to north side May 12th
- Underground work complete
- Electrical ongoing
- Prepping road for pavement
- Paving June 20th
- Signs and pavement markings the week of the 23rd
- Switched to north side May 12th
- Underground work complete
- Electrical ongoing
- Prepping road for pavement
- Paving June 20th
- Signs and pavement markings the week of the 23rd
This project is substantially complete.
-
Share June 13, 2025 on Facebook
Share June 13, 2025 on X (formerly Twitter)
Share June 13, 2025 on Linkedin
Email June 13, 2025 link
- Switched to north side May 12th.
- Underground work complete.
- Electrical ongoing.
- Prepping for concrete.
- Veolia working on services.
- Switched to north side May 12th.
- Underground work complete.
- Electrical ongoing.
- Prepping for concrete.
- Veolia working on services.
This project is substantially complete.
-
Share June 6, 2025 on Facebook
Share June 6, 2025 on X (formerly Twitter)
Share June 6, 2025 on Linkedin
Email June 6, 2025 link
- Switched to north side May 12th.
- Underground work complete.
- Electrical ongoing.
- Prepping for concrete.
- Veolia working on services.
- Switched to north side May 12th.
- Underground work complete.
- Electrical ongoing.
- Prepping for concrete.
- Veolia working on services.
This project is substantially complete.
-
Share May 30, 2025 on Facebook
Share May 30, 2025 on X (formerly Twitter)
Share May 30, 2025 on Linkedin
Email May 30, 2025 link
- Switched to north side May 12th.
- Removal of road and sidewalk.
- Electrical work ongoing.
- Underground work once removals are complete.
- Switched to north side May 12th.
- Removal of road and sidewalk.
- Electrical work ongoing.
- Underground work once removals are complete.
This project is substantially complete.
-
Share May 23, 2025 on Facebook
Share May 23, 2025 on X (formerly Twitter)
Share May 23, 2025 on Linkedin
Email May 23, 2025 link
- Switched to north side May 12th.
- Removal of road and sidewalk.
- Electrical work ongoing.
- Underground work once removals are complete.
- Switched to north side May 12th.
- Removal of road and sidewalk.
- Electrical work ongoing.
- Underground work once removals are complete.
This project is substantially complete.
-
Share May 16, 2025 on Facebook
Share May 16, 2025 on X (formerly Twitter)
Share May 16, 2025 on Linkedin
Email May 16, 2025 link
- Switched to North side May 12th.
- Removal of road and sidewalk.
- Electrical work ongoing.
- Underground work once removals are complete.
- Switched to North side May 12th.
- Removal of road and sidewalk.
- Electrical work ongoing.
- Underground work once removals are complete.
This project is substantially complete.
-
Share May 8, 2025 on Facebook
Share May 8, 2025 on X (formerly Twitter)
Share May 8, 2025 on Linkedin
Email May 8, 2025 link
- Contractor working on Pleasanton Ave and 21st St.
- Placing base material.
- Curb and gutter being placed.
- Paving complete on south side.
- Ped ramps ongoing.
- Switching to north side May 12th.
- Contractor working on Pleasanton Ave and 21st St.
- Placing base material.
- Curb and gutter being placed.
- Paving complete on south side.
- Ped ramps ongoing.
- Switching to north side May 12th.
This project is substantially complete.
-
Share May 2, 2025 on Facebook
Share May 2, 2025 on X (formerly Twitter)
Share May 2, 2025 on Linkedin
Email May 2, 2025 link
- Contractor working on Pleasanton Ave and 21st St.
- Placing base material.
- Curb and gutter being placed.
- Paving complete on south side.
- Ped ramps ongoing.
- Contractor working on Pleasanton Ave and 21st St.
- Placing base material.
- Curb and gutter being placed.
- Paving complete on south side.
- Ped ramps ongoing.
This project is substantially complete.
-
Share April 25, 2025 on Facebook
Share April 25, 2025 on X (formerly Twitter)
Share April 25, 2025 on Linkedin
Email April 25, 2025 link
- Notice to proceed was March 10th.
- Contractor working on Pleasanton Ave and 21st St.
- Placing base material.
- Curb and gutter being placed.
- Paving anticipated April 30th.
- Notice to proceed was March 10th.
- Contractor working on Pleasanton Ave and 21st St.
- Placing base material.
- Curb and gutter being placed.
- Paving anticipated April 30th.
This project is substantially complete.