State and 21st Streets Pedestrian Crossing Project

Share State and 21st Streets Pedestrian Crossing Project on Facebook Share State and 21st Streets Pedestrian Crossing Project on Twitter Share State and 21st Streets Pedestrian Crossing Project on Linkedin Email State and 21st Streets Pedestrian Crossing Project link

Starting as early as March, the Ada County Highway District (ACHD) will begin construction on the State Street and 21st Street Pedestrian Crossing project. The purpose of this project is to improve safety and increase connectivity for pedestrians. Construction is expected to be complete late summer of 2025.*

Project Description

  • Install an enhanced pedestrian crossing at State Street and 21st Street
  • Improve pavement markings
  • Install bulb-outs and reconstruct adjacent pedestrian ramps to meet modern standards
  • Update streetlights for enhanced visibility and safety
  • Widen sidewalks on the north side of State Street, 21st Street, and Pleasanton Avenue to improve accessibility and functionality

Construction Impacts

  • Temporary road closures
  • Pedestrian detours and sidewalk closures
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners and businesses to minimize impacts

*Construction schedules may change.

Starting as early as March, the Ada County Highway District (ACHD) will begin construction on the State Street and 21st Street Pedestrian Crossing project. The purpose of this project is to improve safety and increase connectivity for pedestrians. Construction is expected to be complete late summer of 2025.*

Project Description

  • Install an enhanced pedestrian crossing at State Street and 21st Street
  • Improve pavement markings
  • Install bulb-outs and reconstruct adjacent pedestrian ramps to meet modern standards
  • Update streetlights for enhanced visibility and safety
  • Widen sidewalks on the north side of State Street, 21st Street, and Pleasanton Avenue to improve accessibility and functionality

Construction Impacts

  • Temporary road closures
  • Pedestrian detours and sidewalk closures
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners and businesses to minimize impacts

*Construction schedules may change.

  • April 4, 2025

    Share April 4, 2025 on Facebook Share April 4, 2025 on Twitter Share April 4, 2025 on Linkedin Email April 4, 2025 link
    04 Apr 2025
    • Contractor working on Pleasanton Ave and 21st St.
    • Excavation ongoing.
    • Conduits ongoing.
    • Storm drain pipe ongoing.
  • March 28, 2025

    Share March 28, 2025 on Facebook Share March 28, 2025 on Twitter Share March 28, 2025 on Linkedin Email March 28, 2025 link
    28 Mar 2025
    • Will be working on Pleasanton Ave and 21st St.
    • Excavation ongoing.
    • Conduits being placed starting March 24th.
  • March 20, 2025

    Share March 20, 2025 on Facebook Share March 20, 2025 on Twitter Share March 20, 2025 on Linkedin Email March 20, 2025 link
    20 Mar 2025
    • Will be working on Pleasanton Ave and 21st St.
    • Removals ongoing.
    • Conduits being placed starting March 24th.
  • March 14, 2025

    Share March 14, 2025 on Facebook Share March 14, 2025 on Twitter Share March 14, 2025 on Linkedin Email March 14, 2025 link
    14 Mar 2025
    • Notice to proceed was March 10th.
    • Will be working on Pleasanton Ave and 21st St.
  • March 6, 2025

    Share March 6, 2025 on Facebook Share March 6, 2025 on Twitter Share March 6, 2025 on Linkedin Email March 6, 2025 link
    06 Mar 2025
    • Notice to proceed is anticipated for March 10th.
    • Will be working on Pleasanton Ave and 21st St.