May 8, 2025
- Contractor working on Pleasanton Ave and 21st St.
- Placing base material.
- Curb and gutter being placed.
- Paving complete on south side.
- Ped ramps ongoing.
- Switching to north side May 12th.
Share May 8, 2025 on Facebook
Share May 8, 2025 on X (formerly Twitter)
Share May 8, 2025 on Linkedin
Email May 8, 2025 link
This project is substantially complete.