  • 8th Street electrical/fiber work ongoing.
  • Fiber swap is scheduled for the weekend of July 20th.
  • Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
  • Contractor has moved east and continues to prep road base.
  • Prepping for concrete paving ongoing – tentatively scheduled for August 21-22nd.
Share August 15, 2024 on Facebook Share August 15, 2024 on Twitter Share August 15, 2024 on Linkedin Email August 15, 2024 link

This project is substantially complete. 