State Street, 8th Street to 4th Street

Share State Street, 8th Street to 4th Street on Facebook Share State Street, 8th Street to 4th Street on Twitter Share State Street, 8th Street to 4th Street on Linkedin Email State Street, 8th Street to 4th Street link
  • Reconstruct State Street between 8th and 4th streets.
  • Upgrade all three traffic signals on this section of State St.
  • Construct bulb-outs for shorter pedestrian crossings and better visibility.
  • Add vegetated bioretention facilities for stormwater treatment.
  • Upgrade the existing enhanced crosswalk behind the Idaho State Capitol building to an overhead Rectangular Rapid Flashing Beacon.
  • Reconstruct State Street between 8th and 4th streets.
  • Upgrade all three traffic signals on this section of State St.
  • Construct bulb-outs for shorter pedestrian crossings and better visibility.
  • Add vegetated bioretention facilities for stormwater treatment.
  • Upgrade the existing enhanced crosswalk behind the Idaho State Capitol building to an overhead Rectangular Rapid Flashing Beacon.
  • November 15, 2024

    Share November 15, 2024 on Facebook Share November 15, 2024 on Twitter Share November 15, 2024 on Linkedin Email November 15, 2024 link
    • Project includes work on State Street between 4th Street and 8th Street.
    • Concrete has been placed up to 8th Street.
    • Asphalt transitions were placed this week.
    • Project is targeting being substantially complete by the end of the month.
    • Landscape work ongoing.
  • November 7, 2024

    Share November 7, 2024 on Facebook Share November 7, 2024 on Twitter Share November 7, 2024 on Linkedin Email November 7, 2024 link
    • Concrete has been placed up to 8th Street.
    • Asphalt transitions to be placed next week.
    • Project is targeting being substantially complete by the end of the month.
    • Landscape work ongoing.
  • November 1, 2024

    Share November 1, 2024 on Facebook Share November 1, 2024 on Twitter Share November 1, 2024 on Linkedin Email November 1, 2024 link
    • Contractor has moved east and continues to prep road base from 6th to 8th.
    • 6th Street intersection concrete placement complete.
    • 4th and 5th intersections are open to north/south traffic.
    • Concrete placement between 6th and 8th is complete.
    • Sidewalks and ped ramp work ongoing between 6th and 8th.
    • Landscape work ongoing.
  • October 24, 2024

    Share October 24, 2024 on Facebook Share October 24, 2024 on Twitter Share October 24, 2024 on Linkedin Email October 24, 2024 link
    • Contractor has moved east and continues to prep road base from 6th to 8th.
    • 6th Street Intersection concrete placement scheduled for October 23rd.
    • 4th and 5th intersections are open to north/south traffic.
    • Prepping for concrete placement between 6th and 8th.
    • Sidewalks and ped ramp work ongoing between 6th and 8th.
    • Landscape work ongoing.
  • October 17, 2024

    Share October 17, 2024 on Facebook Share October 17, 2024 on Twitter Share October 17, 2024 on Linkedin Email October 17, 2024 link
    • 8th Street electrical/fiber work complete.
    • Contractor has moved east and continues to prep road base from 6th to 8th.
    • Planning to concrete pave October 18th from 5th to 6th.
    • 4th and 5th intersections are open to north/south traffic.
    • Sidewalks and pedestrian ramp work ongoing between 6th and 8th.
    • Landscapers to follow.
  • October 10, 2024

    Share October 10, 2024 on Facebook Share October 10, 2024 on Twitter Share October 10, 2024 on Linkedin Email October 10, 2024 link
    • 8th Street electrical/fiber work complete.
    • Contractor has moved east and continues to prep road base from 6th to 8th.
    • Planning to concrete pave between 5th and 6th mid-October.
    • 4th and 5th intersections are open to north/south traffic.
    • Sidewalks and pedestrian ramp work ongoing between 4th, 5th and 6th.
    • Landscapers to follow.
  • October 7, 2024 - Updated Detour Map & Information

    Share October 7, 2024 - Updated Detour Map & Information on Facebook Share October 7, 2024 - Updated Detour Map & Information on Twitter Share October 7, 2024 - Updated Detour Map & Information on Linkedin Email October 7, 2024 - Updated Detour Map & Information link
    • State/5th and State/4th are now open to North and Southbound traffic, please see the updated detour map below.

  • October 4, 2024

    Share October 4, 2024 on Facebook Share October 4, 2024 on Twitter Share October 4, 2024 on Linkedin Email October 4, 2024 link
    • 8th Street electrical/fiber work complete.
    • Contractor has moved east and continues to prep road base from 6th to 8th.
    • Concrete paving complete between 4th and 5th St.
    • Anticipate opening 4th and 5th intersections as early as next week.
    • Power and fiber for signals nearly complete.
    • Sidewalks and ped ramp work ongoing between 4th and 5th.
    • Landscapers to follow.
  • September 26, 2024

    Share September 26, 2024 on Facebook Share September 26, 2024 on Twitter Share September 26, 2024 on Linkedin Email September 26, 2024 link
    • 8th Street electrical/fiber work ongoing.
    • Idaho Power vault has been lowered.
    • Contractor has moved east and continues to prep road base from 6th to 8th.
    • Concrete paving complete between 4th and 5th St.
    • South side of 5th complete.
    • Power and fiber for signals nearly complete.
    • Sidewalks and ped ramp work ongoing between 4th and 5th. Landscapers to follow.
  • September 20, 2024

    Share September 20, 2024 on Facebook Share September 20, 2024 on Twitter Share September 20, 2024 on Linkedin Email September 20, 2024 link
    • 8th Street electrical/fiber work ongoing.
    • Idaho Power vault has been lowered.
    • Contractor has moved east and continues to prep road base from 6th to 8th.
    • Concrete paving complete between 4th and 5th St.
    • South side of 5th complete.
    • Power and fiber for signals nearly complete.
    • Sidewalks and ped ramp work ongoing between 4th and 5th.
    • Landscapers to follow.
Page last updated: 15 Nov 2024, 10:53 AM