State Street, 8th Street to 4th Street

Share State Street, 8th Street to 4th Street on Facebook Share State Street, 8th Street to 4th Street on Twitter Share State Street, 8th Street to 4th Street on Linkedin Email State Street, 8th Street to 4th Street link
  • Reconstruct State Street between 8th and 4th streets.
  • Upgrade all three traffic signals on this section of State St.
  • Construct bulb-outs for shorter pedestrian crossings and better visibility.
  • Add vegetated bioretention facilities for stormwater treatment.
  • Upgrade the existing enhanced crosswalk behind the Idaho State Capitol building to an overhead Rectangular Rapid Flashing Beacon.
  • Reconstruct State Street between 8th and 4th streets.
  • Upgrade all three traffic signals on this section of State St.
  • Construct bulb-outs for shorter pedestrian crossings and better visibility.
  • Add vegetated bioretention facilities for stormwater treatment.
  • Upgrade the existing enhanced crosswalk behind the Idaho State Capitol building to an overhead Rectangular Rapid Flashing Beacon.
  • July 26, 2024

    Share July 26, 2024 on Facebook Share July 26, 2024 on Twitter Share July 26, 2024 on Linkedin Email July 26, 2024 link
    • Project includes work on State Street between 4th Street and 8th Street
      • 8th Street electrical/fiber work ongoing.
      • Fiber swap is scheduled for the weekend of July 20th.
      • Idaho Power vault needs to be lowered.
      • IP working with engineer consultant to retrofit box to meet new grades.
      • Contractor completed demo on State and 8th.
      • Excavation complete, on the north side, in preparation for base materials.
      • Contractor has moved east and started to prep for road base while Idaho Power sorts out the vault issue on State and 8th.
  • July 19, 2024

    Share July 19, 2024 on Facebook Share July 19, 2024 on Twitter Share July 19, 2024 on Linkedin Email July 19, 2024 link
    • 8th Street electrical/fiber work ongoing – Fiber swap is scheduled for the weekend of July 20th.
    • Contractor completed demo on State and 8th this week.
    • Excavation started this week, on the north side, in preparation for base materials.
    • Idaho Power underground work is ongoing.
  • July 17, 2024

    Share July 17, 2024 on Facebook Share July 17, 2024 on Twitter Share July 17, 2024 on Linkedin Email July 17, 2024 link

    An unforeseen utility conflict has been found at the State Street and 8th Street intersection. It is anticipated to take two months for the utility’s contractor to resolve. ACHD construction crews will now focus on the east end of the project.

    The State Street and 4th Street intersection will be paved first and then paving will continue moving west.

    As the intersections are paved, ACHD plans to open them to north/south traffic.

  • July 12, 2024

    Share July 12, 2024 on Facebook Share July 12, 2024 on Twitter Share July 12, 2024 on Linkedin Email July 12, 2024 link
    • Project includes work on State Street between 4th Street and 8th Street - Veolia water work complete.
    • 8th Street electrical/fiber work ongoing.
    • Fiber swap is scheduled for the weekend of July 20th.
    • Contractor completed demo on State and 8th this week.
    • Excavation started this week, on the north side, in preparation for base materials.
  • June 28, 2024

    Share June 28, 2024 on Facebook Share June 28, 2024 on Twitter Share June 28, 2024 on Linkedin Email June 28, 2024 link
    • Veolia water work started April 1st and is on-going.
    • State and 8th intersection work is complete.
    • 8th Street electrical work ongoing.
    • Contractor completed demo on State and 8th this week.
  • June 21, 2024

    Share June 21, 2024 on Facebook Share June 21, 2024 on Twitter Share June 21, 2024 on Linkedin Email June 21, 2024 link
    • Project includes work on State Street between 4th Street and 8th Street.
    • Veolia water work started April 1st and is on-going.
    • State and 8th intersection work is complete.
    • 8th Street electrical work ongoing.
    • Contractor completed demo on State and 8th this week.
  • June 14, 2024

    Share June 14, 2024 on Facebook Share June 14, 2024 on Twitter Share June 14, 2024 on Linkedin Email June 14, 2024 link

    Project includes work on State Street between 4th Street and 8th Street

    • Veolia water work started April 1st and is on-going
      • State and 8th intersection work is complete
    • 8th Street utility work ongoing.
    • Electrical work ongoing.
    • Contractor started demo on State and 8th this week.
  • June 7, 2024

    Share June 7, 2024 on Facebook Share June 7, 2024 on Twitter Share June 7, 2024 on Linkedin Email June 7, 2024 link
    • Veolia water work started April 1st and is on-going
      • State and 8th intersection work is complete minus a hydrant tieover
    • 8th Street utility work ongoing
    • Electrical work ongoing
    • Contractor expects to start demo on State and 8th as early as next week
  • May 31, 2024

    Share May 31, 2024 on Facebook Share May 31, 2024 on Twitter Share May 31, 2024 on Linkedin Email May 31, 2024 link
    • Veolia water work started April 1st and is on-going.
    • 8th Street utility work ongoing.
    • Electrical work ongoing.
  • May 23, 2024

    Share May 23, 2024 on Facebook Share May 23, 2024 on Twitter Share May 23, 2024 on Linkedin Email May 23, 2024 link
    • Veolia water work started April 1st and is on-going.
    • 8th Street utility work ongoing.
    • Electrical work ongoing.
    • Pole bases on 5th and 6th have been placed.
Page last updated: 26 Jul 2024, 09:46 AM