August 2, 2024
- 8th Street electrical/fiber work ongoing – Fiber swap is scheduled for the weekend of July 20th.
- Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and started to prep for road base while Idaho Power sorts out the vault issue on State and 8th.
- Prepping for concrete paving ongoing.