August 30, 2024

  • 8th Street electrical/fiber work ongoing.
  • Fiber swap is scheduled for the weekend of July 20th.
  • Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
  • Contractor has moved east and continues to prep road base from 6th to 8th.
  • Concrete paving started between 4th and 5th St.
  • Power and fiber for signals ongoing.
Share August 30, 2024 on Facebook Share August 30, 2024 on Twitter Share August 30, 2024 on Linkedin Email August 30, 2024 link

This project is substantially complete. 

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>