August 30, 2024
- 8th Street electrical/fiber work ongoing.
- Fiber swap is scheduled for the weekend of July 20th.
- Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and continues to prep road base from 6th to 8th.
- Concrete paving started between 4th and 5th St.
- Power and fiber for signals ongoing.
Share August 30, 2024 on Facebook
Share August 30, 2024 on X (formerly Twitter)
Share August 30, 2024 on Linkedin
Email August 30, 2024 link
This project is substantially complete.