August 30, 2024

  • 8th Street electrical/fiber work ongoing.
  • Fiber swap is scheduled for the weekend of July 20th.
  • Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
  • Contractor has moved east and continues to prep road base from 6th to 8th.
  • Concrete paving started between 4th and 5th St.
  • Power and fiber for signals ongoing.