August 9, 2024
- 8th Street electrical/fiber work ongoing.
- Fiber swap is scheduled for the weekend of July 20th.
- Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and started to prep for road base while Idaho Power sorts out the vault issue on State and 8th.
- Prepping for concrete paving ongoing.
Share August 9, 2024 on Facebook
Share August 9, 2024 on X (formerly Twitter)
Share August 9, 2024 on Linkedin
Email August 9, 2024 link
This project is substantially complete.