July 17, 2024

An unforeseen utility conflict has been found at the State Street and 8th Street intersection. It is anticipated to take two months for the utility’s contractor to resolve. ACHD construction crews will now focus on the east end of the project.

The State Street and 4th Street intersection will be paved first and then paving will continue moving west.

As the intersections are paved, ACHD plans to open them to north/south traffic.