  • 8th Street electrical/fiber work ongoing – Fiber swap is scheduled for the weekend of July 20th.
  • Contractor completed demo on State and 8th this week.
  • Excavation started this week, on the north side, in preparation for base materials.
  • Idaho Power underground work is ongoing.