July 19, 2024

  • 8th Street electrical/fiber work ongoing – Fiber swap is scheduled for the weekend of July 20th.
  • Contractor completed demo on State and 8th this week.
  • Excavation started this week, on the north side, in preparation for base materials.
  • Idaho Power underground work is ongoing.
Share July 19, 2024 on Facebook Share July 19, 2024 on Twitter Share July 19, 2024 on Linkedin Email July 19, 2024 link

This project is substantially complete. 