July 19, 2024
- 8th Street electrical/fiber work ongoing – Fiber swap is scheduled for the weekend of July 20th.
- Contractor completed demo on State and 8th this week.
- Excavation started this week, on the north side, in preparation for base materials.
- Idaho Power underground work is ongoing.
Share July 19, 2024 on Facebook
Share July 19, 2024 on X (formerly Twitter)
Share July 19, 2024 on Linkedin
Email July 19, 2024 link
This project is substantially complete.