July 26, 2024
- Project includes work on State Street between 4th Street and 8th Street
- 8th Street electrical/fiber work ongoing.
- Fiber swap is scheduled for the weekend of July 20th.
- Idaho Power vault needs to be lowered.
- IP working with engineer consultant to retrofit box to meet new grades.
- Contractor completed demo on State and 8th.
- Excavation complete, on the north side, in preparation for base materials.
- Contractor has moved east and started to prep for road base while Idaho Power sorts out the vault issue on State and 8th.