July 26, 2024

  • Project includes work on State Street between 4th Street and 8th Street
    • 8th Street electrical/fiber work ongoing.
    • Fiber swap is scheduled for the weekend of July 20th.
    • Idaho Power vault needs to be lowered.
    • IP working with engineer consultant to retrofit box to meet new grades.
    • Contractor completed demo on State and 8th.
    • Excavation complete, on the north side, in preparation for base materials.
    • Contractor has moved east and started to prep for road base while Idaho Power sorts out the vault issue on State and 8th.