November 1, 2024
- Contractor has moved east and continues to prep road base from 6th to 8th.
- 6th Street intersection concrete placement complete.
- 4th and 5th intersections are open to north/south traffic.
- Concrete placement between 6th and 8th is complete.
- Sidewalks and ped ramp work ongoing between 6th and 8th.
- Landscape work ongoing.