  • Contractor has moved east and continues to prep road base from 6th to 8th.
  • 6th Street intersection concrete placement complete.
  • 4th and 5th intersections are open to north/south traffic.
  • Concrete placement between 6th and 8th is complete.
  • Sidewalks and ped ramp work ongoing between 6th and 8th.
  • Landscape work ongoing.
Share November 1, 2024 on Facebook Share November 1, 2024 on Twitter Share November 1, 2024 on Linkedin Email November 1, 2024 link

This project is substantially complete. 