November 15, 2024

  • Project includes work on State Street between 4th Street and 8th Street.
  • Concrete has been placed up to 8th Street.
  • Asphalt transitions were placed this week.
  • Project is targeting being substantially complete by the end of the month.
  • Landscape work ongoing.