October 17, 2024
- 8th Street electrical/fiber work complete.
- Contractor has moved east and continues to prep road base from 6th to 8th.
- Planning to concrete pave October 18th from 5th to 6th.
- 4th and 5th intersections are open to north/south traffic.
- Sidewalks and pedestrian ramp work ongoing between 6th and 8th.
- Landscapers to follow.
Share October 17, 2024 on Facebook
Share October 17, 2024 on Twitter
Share October 17, 2024 on Linkedin
Email October 17, 2024 link
This project is substantially complete.