October 17, 2024
- 8th Street electrical/fiber work complete.
- Contractor has moved east and continues to prep road base from 6th to 8th.
- Planning to concrete pave October 18th from 5th to 6th.
- 4th and 5th intersections are open to north/south traffic.
- Sidewalks and pedestrian ramp work ongoing between 6th and 8th.
- Landscapers to follow.
Share October 17, 2024 on Facebook
Share October 17, 2024 on X (formerly Twitter)
Share October 17, 2024 on Linkedin
Email October 17, 2024 link
This project is substantially complete.