October 24, 2024

  • Contractor has moved east and continues to prep road base from 6th to 8th.
  • 6th Street Intersection concrete placement scheduled for October 23rd.
  • 4th and 5th intersections are open to north/south traffic.
  • Prepping for concrete placement between 6th and 8th.
  • Sidewalks and ped ramp work ongoing between 6th and 8th.
  • Landscape work ongoing.
Share October 24, 2024 on Facebook Share October 24, 2024 on Twitter Share October 24, 2024 on Linkedin Email October 24, 2024 link

This project is substantially complete. 