  • 8th Street electrical/fiber work complete.
  • Contractor has moved east and continues to prep road base from 6th to 8th.
  • Concrete paving complete between 4th and 5th St.
  • Anticipate opening 4th and 5th intersections as early as next week.
  • Power and fiber for signals nearly complete.
  • Sidewalks and ped ramp work ongoing between 4th and 5th.
  • Landscapers to follow.