September 13, 2024

13 Sep 2024
  • 8th Street electrical/fiber work ongoing.
  • Idaho Power vault needs to be lowered.
  • IP working with engineer consultant to retrofit box to meet new grades.
  • Contractor has moved east and continues to prep road base from 6th to 8th.
  • Concrete paving complete between 4th and 5th St. South side of 5th complete.
  • Power and fiber for signals nearly complete.
  • Sidewalks and ped ramp work started between 4th and 5th.
  • Landscapers to follow.
Share September 13, 2024 on Facebook Share September 13, 2024 on Twitter Share September 13, 2024 on Linkedin Email September 13, 2024 link

This project is substantially complete. 

#<Object:0x000000002717f3f0>