September 13, 2024

  • 8th Street electrical/fiber work ongoing.
  • Idaho Power vault needs to be lowered.
  • IP working with engineer consultant to retrofit box to meet new grades.
  • Contractor has moved east and continues to prep road base from 6th to 8th.
  • Concrete paving complete between 4th and 5th St. South side of 5th complete.
  • Power and fiber for signals nearly complete.
  • Sidewalks and ped ramp work started between 4th and 5th.
  • Landscapers to follow.