September 20, 2024
- 8th Street electrical/fiber work ongoing.
- Idaho Power vault has been lowered.
- Contractor has moved east and continues to prep road base from 6th to 8th.
- Concrete paving complete between 4th and 5th St.
- South side of 5th complete.
- Power and fiber for signals nearly complete.
- Sidewalks and ped ramp work ongoing between 4th and 5th.
- Landscapers to follow.