September 20, 2024

  • 8th Street electrical/fiber work ongoing.
  • Idaho Power vault has been lowered.
  • Contractor has moved east and continues to prep road base from 6th to 8th.
  • Concrete paving complete between 4th and 5th St.
  • South side of 5th complete.
  • Power and fiber for signals nearly complete.
  • Sidewalks and ped ramp work ongoing between 4th and 5th.
  • Landscapers to follow.
Share September 20, 2024 on Facebook Share September 20, 2024 on Twitter Share September 20, 2024 on Linkedin Email September 20, 2024 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>