September 6, 2024

  • 8th Street electrical/fiber work ongoing.
  • Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
  • Contractor has moved east and continues to prep road base from 6th to 8th.
  • Concrete paving complete between 4th and 5th St.
  • South side of 5th will be paved on Friday September 6th.
  • Power and fiber for signals nearly complete.
  • Sidewalks and ped ramp work started between 4th and 5th. Landscapers to follow.
Share September 6, 2024 on Facebook Share September 6, 2024 on X (formerly Twitter) Share September 6, 2024 on Linkedin Email September 6, 2024 link

This project is substantially complete. 