September 6, 2024
- 8th Street electrical/fiber work ongoing.
- Idaho Power vault needs to be lowered. IP working with engineer consultant to retrofit box to meet new grades.
- Contractor has moved east and continues to prep road base from 6th to 8th.
- Concrete paving complete between 4th and 5th St.
- South side of 5th will be paved on Friday September 6th.
- Power and fiber for signals nearly complete.
- Sidewalks and ped ramp work started between 4th and 5th. Landscapers to follow.