April 2, 2026

  • Traffic calming plan has been implemented in the neighborhoods north of State Street.
  • Eastbound traffic is on the south side of State Street.
  • Westbound traffic was shifted onto the new pavement on the north side of State Street on the night of March 31st.
  • The work zone is currently in the middle of State Street.
  • Left turns have been eliminated through the work zone.
  • Work on-going on Pierce Park.
  • Contractor is setting guardrail to protect the work zone, on-going through the week of April 6th.
  • Asphalt milling in the center work zone is scheduled for the week of April 6th.