State Street and Pierce Park Lane Intersection

Share State Street and Pierce Park Lane Intersection on Facebook Share State Street and Pierce Park Lane Intersection on X (formerly Twitter) Share State Street and Pierce Park Lane Intersection on Linkedin Email State Street and Pierce Park Lane Intersection link

This project is substantially complete. 

The Ada County Highway District (ACHD) is designing future improvements for the State Street and Pierce Park Lane Intersection. This project aims to improve safety and connectivity for all users, accommodate future traffic volumes, and incorporate ideas and concerns gathered from the public.

The improvements for State Street and Pierce Park Lane include:

  • Realigning Pierce Park Lane to improve safety and provide better line of sight for drivers
  • Widening State Street within the project limits and add medians where necessary for safety
  • Providing U-turns at multiple locations
  • Adding continuous multi-use pathways for pedestrians and cyclists
  • Adding additional crosswalk on State Street

The Ada County Highway District (ACHD) is designing future improvements for the State Street and Pierce Park Lane Intersection. This project aims to improve safety and connectivity for all users, accommodate future traffic volumes, and incorporate ideas and concerns gathered from the public.

The improvements for State Street and Pierce Park Lane include:

  • Realigning Pierce Park Lane to improve safety and provide better line of sight for drivers
  • Widening State Street within the project limits and add medians where necessary for safety
  • Providing U-turns at multiple locations
  • Adding continuous multi-use pathways for pedestrians and cyclists
  • Adding additional crosswalk on State Street

This project is substantially complete. 

  • November 6, 2026

    Share November 6, 2026 on Facebook Share November 6, 2026 on X (formerly Twitter) Share November 6, 2026 on Linkedin Email November 6, 2026 link
    • The left-turn lane at Pierce Park was opened October 16th.
    • Concrete work for curb, gutter, & sidewalk is complete.
    • Concrete paving and mainline asphalt paving are complete.
    • Permanent striping and concrete island construction is nearly complete.
    • Minor work with daytime lane closures will continue into November, including swale construction, landscape repair, etc.
    • Project is expected to be substantially complete by November 13th.
    • The speed limit will be restored to 40 MPH by November 13th.
    • The left-turn lane at Pierce Park was opened October 16th.
    • Concrete work for curb, gutter, & sidewalk is complete.
    • Concrete paving and mainline asphalt paving are complete.
    • Permanent striping and concrete island construction is nearly complete.
    • Minor work with daytime lane closures will continue into November, including swale construction, landscape repair, etc.
    • Project is expected to be substantially complete by November 13th.
    • The speed limit will be restored to 40 MPH by November 13th.

    This project is substantially complete. 

  • October 30, 2026

    Share October 30, 2026 on Facebook Share October 30, 2026 on X (formerly Twitter) Share October 30, 2026 on Linkedin Email October 30, 2026 link
    • Traffic has been shifted into its permanent configuration.
    • The left-turn lane at Pierce Park was opened October 16th.
    • Concrete work for curb, gutter, & sidewalk is nearly complete.
    • Concrete paving and mainline asphalt paving are complete.
    • Permanent striping and concrete island construction is nearly complete.
    • Minor work with daytime lane closures will continue into November, including swale construction, landscape repair, etc.
    • Traffic has been shifted into its permanent configuration.
    • The left-turn lane at Pierce Park was opened October 16th.
    • Concrete work for curb, gutter, & sidewalk is nearly complete.
    • Concrete paving and mainline asphalt paving are complete.
    • Permanent striping and concrete island construction is nearly complete.
    • Minor work with daytime lane closures will continue into November, including swale construction, landscape repair, etc.

    This project is substantially complete. 

  • October 22, 2026

    Share October 22, 2026 on Facebook Share October 22, 2026 on X (formerly Twitter) Share October 22, 2026 on Linkedin Email October 22, 2026 link
    • Traffic was shifted into its permanent configuration on October 16th.
    • The left-turn lane at Pierce Park was opened October 16th.
    • Concrete work for curb, gutter, & sidewalk is nearly complete.
    • Concrete paving and mainline asphalt paving are complete.
    • Permanent striping and concrete island construction will be on-going throughout October.
    • Minor work with daytime lane closures will continue into November, including swale construction, landscape repair, etc.
    • Traffic was shifted into its permanent configuration on October 16th.
    • The left-turn lane at Pierce Park was opened October 16th.
    • Concrete work for curb, gutter, & sidewalk is nearly complete.
    • Concrete paving and mainline asphalt paving are complete.
    • Permanent striping and concrete island construction will be on-going throughout October.
    • Minor work with daytime lane closures will continue into November, including swale construction, landscape repair, etc.

    This project is substantially complete. 

  • October 16, 2026

    Share October 16, 2026 on Facebook Share October 16, 2026 on X (formerly Twitter) Share October 16, 2026 on Linkedin Email October 16, 2026 link
    • Concrete work for curb, gutter, & sidewalk is nearly complete.
    • Concrete paving and mainline asphalt paving are complete.
    • Permanent striping and concrete island construction will be on-going throughout October.
    • Traffic was shifted into its permanent configuration on October 16th.
    • The left-turn lane at Pierce Park was opened October 16th.
    • Minor work with daytime lane closures will continue into November, including swale construction, landscape repair, etc.
    • Concrete work for curb, gutter, & sidewalk is nearly complete.
    • Concrete paving and mainline asphalt paving are complete.
    • Permanent striping and concrete island construction will be on-going throughout October.
    • Traffic was shifted into its permanent configuration on October 16th.
    • The left-turn lane at Pierce Park was opened October 16th.
    • Minor work with daytime lane closures will continue into November, including swale construction, landscape repair, etc.

    This project is substantially complete. 

  • October 9, 2026

    Share October 9, 2026 on Facebook Share October 9, 2026 on X (formerly Twitter) Share October 9, 2026 on Linkedin Email October 9, 2026 link
    • Concrete work for curb, gutter, & sidewalk is nearly complete.
    • Concrete paving and mainline asphalt paving are complete.
    • Permanent striping and concrete island construction will be on-going throughout October.
    • Traffic will be shifted into its permanent configuration as early as October 16th, weather dependent.
    • The left-turn lane at Pierce Park is anticipated to re-open as early as October 16th, weather dependent.
    • Minor work will continue into November, including swale construction, landscape repair, etc.
    • Concrete work for curb, gutter, & sidewalk is nearly complete.
    • Concrete paving and mainline asphalt paving are complete.
    • Permanent striping and concrete island construction will be on-going throughout October.
    • Traffic will be shifted into its permanent configuration as early as October 16th, weather dependent.
    • The left-turn lane at Pierce Park is anticipated to re-open as early as October 16th, weather dependent.
    • Minor work will continue into November, including swale construction, landscape repair, etc.

    This project is substantially complete. 

  • October 2, 2026

    Share October 2, 2026 on Facebook Share October 2, 2026 on X (formerly Twitter) Share October 2, 2026 on Linkedin Email October 2, 2026 link
    • Placement of base gravels started August 3rd and is on-going.
    • Concrete work for curb & gutter started August 18th and is on-going.
    • Concrete paving is complete.
    • Mainline asphalt paving is complete.
    • Permanent striping and concrete island construction is scheduled for October.
    • The left-turn lane at Pierce Park is anticipated to re-open by the end of October.
    • Minor work will continue into November, including swale construction, landscape repair, etc.
    • Placement of base gravels started August 3rd and is on-going.
    • Concrete work for curb & gutter started August 18th and is on-going.
    • Concrete paving is complete.
    • Mainline asphalt paving is complete.
    • Permanent striping and concrete island construction is scheduled for October.
    • The left-turn lane at Pierce Park is anticipated to re-open by the end of October.
    • Minor work will continue into November, including swale construction, landscape repair, etc.

    This project is substantially complete. 

  • September 24, 2026

    Share September 24, 2026 on Facebook Share September 24, 2026 on X (formerly Twitter) Share September 24, 2026 on Linkedin Email September 24, 2026 link
    • Placement of base gravels started August 3rd and is on-going.
    • Concrete work for curb & gutter started August 18th and is on-going.
    • Concrete paving is complete.
    • Asphalt paving is scheduled for late September or early October.
    • Permanent striping and concrete island construction is scheduled for October.
    • The left-turn lane at Pierce Park is anticipated to re-open by the end of October.
    • Minor work will continue into November, including swale construction, landscape repair, etc.
    • Placement of base gravels started August 3rd and is on-going.
    • Concrete work for curb & gutter started August 18th and is on-going.
    • Concrete paving is complete.
    • Asphalt paving is scheduled for late September or early October.
    • Permanent striping and concrete island construction is scheduled for October.
    • The left-turn lane at Pierce Park is anticipated to re-open by the end of October.
    • Minor work will continue into November, including swale construction, landscape repair, etc.

    This project is substantially complete. 

  • September 17, 2026

    Share September 17, 2026 on Facebook Share September 17, 2026 on X (formerly Twitter) Share September 17, 2026 on Linkedin Email September 17, 2026 link
    • Placement of base gravels started August 3rd and is on-going.
    • Concrete work for curb & gutter started August 18th and is on-going.
    • Concrete paving is complete.
    • Asphalt paving is scheduled for late September or early October.
    • Permanent striping and concrete island construction is scheduled for October.
    • The left-turn lane at Pierce Park is anticipated to re-open by the end of October.
    • Minor work will continue into November, including swale construction, landscape repair, etc.
    • Placement of base gravels started August 3rd and is on-going.
    • Concrete work for curb & gutter started August 18th and is on-going.
    • Concrete paving is complete.
    • Asphalt paving is scheduled for late September or early October.
    • Permanent striping and concrete island construction is scheduled for October.
    • The left-turn lane at Pierce Park is anticipated to re-open by the end of October.
    • Minor work will continue into November, including swale construction, landscape repair, etc.

    This project is substantially complete. 

  • September 11, 2026

    Share September 11, 2026 on Facebook Share September 11, 2026 on X (formerly Twitter) Share September 11, 2026 on Linkedin Email September 11, 2026 link
    • Utility work for the project is complete.
    • Placement of base gravels started August 3rd and is on-going.
    • Concrete work for curb & gutter started August 18th and is on-going.
    • Concrete paving is complete.
    • Asphalt paving is scheduled for late September.
    • Permanent striping, concrete island construction, and swale construction is scheduled for October.
    • Utility work for the project is complete.
    • Placement of base gravels started August 3rd and is on-going.
    • Concrete work for curb & gutter started August 18th and is on-going.
    • Concrete paving is complete.
    • Asphalt paving is scheduled for late September.
    • Permanent striping, concrete island construction, and swale construction is scheduled for October.

    This project is substantially complete. 

  • September 3, 2026

    Share September 3, 2026 on Facebook Share September 3, 2026 on X (formerly Twitter) Share September 3, 2026 on Linkedin Email September 3, 2026 link
    • Work on Pierce Park Lane is mostly complete.
    • Utility work for the project is complete.
    • Placement of base gravels started August 3rd and is on-going.
    • Concrete work for curb & gutter started August 18th and is on-going.
    • Concrete paving started September 1st and will be complete by mid-September.
    • Asphalt paving is scheduled for late September.
    • Work on Pierce Park Lane is mostly complete.
    • Utility work for the project is complete.
    • Placement of base gravels started August 3rd and is on-going.
    • Concrete work for curb & gutter started August 18th and is on-going.
    • Concrete paving started September 1st and will be complete by mid-September.
    • Asphalt paving is scheduled for late September.

    This project is substantially complete.