State Street and Pierce Park Lane Intersection

Share State Street and Pierce Park Lane Intersection on Facebook Share State Street and Pierce Park Lane Intersection on X (formerly Twitter) Share State Street and Pierce Park Lane Intersection on Linkedin Email State Street and Pierce Park Lane Intersection link

The Ada County Highway District (ACHD) is designing future improvements for the State Street and Pierce Park Lane Intersection. This project aims to improve safety and connectivity for all users, accommodate future traffic volumes, and incorporate ideas and concerns gathered from the public.

The improvements for State Street and Pierce Park Lane include:

  • Realigning Pierce Park Lane to improve safety and provide better line of sight for drivers
  • Widening State Street within the project limits and add medians where necessary for safety
  • Providing U-turns at multiple locations
  • Adding continuous multi-use pathways for pedestrians and cyclists
  • Adding additional crosswalk on State Street

The Ada County Highway District (ACHD) is designing future improvements for the State Street and Pierce Park Lane Intersection. This project aims to improve safety and connectivity for all users, accommodate future traffic volumes, and incorporate ideas and concerns gathered from the public.

The improvements for State Street and Pierce Park Lane include:

  • Realigning Pierce Park Lane to improve safety and provide better line of sight for drivers
  • Widening State Street within the project limits and add medians where necessary for safety
  • Providing U-turns at multiple locations
  • Adding continuous multi-use pathways for pedestrians and cyclists
  • Adding additional crosswalk on State Street
  • October 2, 2026

    Share October 2, 2026 on Facebook Share October 2, 2026 on X (formerly Twitter) Share October 2, 2026 on Linkedin Email October 2, 2026 link
    • Placement of base gravels started August 3rd and is on-going.
    • Concrete work for curb & gutter started August 18th and is on-going.
    • Concrete paving is complete.
    • Mainline asphalt paving is complete.
    • Permanent striping and concrete island construction is scheduled for October.
    • The left-turn lane at Pierce Park is anticipated to re-open by the end of October.
    • Minor work will continue into November, including swale construction, landscape repair, etc.
    • Placement of base gravels started August 3rd and is on-going.
    • Concrete work for curb & gutter started August 18th and is on-going.
    • Concrete paving is complete.
    • Mainline asphalt paving is complete.
    • Permanent striping and concrete island construction is scheduled for October.
    • The left-turn lane at Pierce Park is anticipated to re-open by the end of October.
    • Minor work will continue into November, including swale construction, landscape repair, etc.
  • September 24, 2026

    Share September 24, 2026 on Facebook Share September 24, 2026 on X (formerly Twitter) Share September 24, 2026 on Linkedin Email September 24, 2026 link
    • Placement of base gravels started August 3rd and is on-going.
    • Concrete work for curb & gutter started August 18th and is on-going.
    • Concrete paving is complete.
    • Asphalt paving is scheduled for late September or early October.
    • Permanent striping and concrete island construction is scheduled for October.
    • The left-turn lane at Pierce Park is anticipated to re-open by the end of October.
    • Minor work will continue into November, including swale construction, landscape repair, etc.
    • Placement of base gravels started August 3rd and is on-going.
    • Concrete work for curb & gutter started August 18th and is on-going.
    • Concrete paving is complete.
    • Asphalt paving is scheduled for late September or early October.
    • Permanent striping and concrete island construction is scheduled for October.
    • The left-turn lane at Pierce Park is anticipated to re-open by the end of October.
    • Minor work will continue into November, including swale construction, landscape repair, etc.
  • September 17, 2026

    Share September 17, 2026 on Facebook Share September 17, 2026 on X (formerly Twitter) Share September 17, 2026 on Linkedin Email September 17, 2026 link
    • Placement of base gravels started August 3rd and is on-going.
    • Concrete work for curb & gutter started August 18th and is on-going.
    • Concrete paving is complete.
    • Asphalt paving is scheduled for late September or early October.
    • Permanent striping and concrete island construction is scheduled for October.
    • The left-turn lane at Pierce Park is anticipated to re-open by the end of October.
    • Minor work will continue into November, including swale construction, landscape repair, etc.
    • Placement of base gravels started August 3rd and is on-going.
    • Concrete work for curb & gutter started August 18th and is on-going.
    • Concrete paving is complete.
    • Asphalt paving is scheduled for late September or early October.
    • Permanent striping and concrete island construction is scheduled for October.
    • The left-turn lane at Pierce Park is anticipated to re-open by the end of October.
    • Minor work will continue into November, including swale construction, landscape repair, etc.
  • September 11, 2026

    Share September 11, 2026 on Facebook Share September 11, 2026 on X (formerly Twitter) Share September 11, 2026 on Linkedin Email September 11, 2026 link
    • Utility work for the project is complete.
    • Placement of base gravels started August 3rd and is on-going.
    • Concrete work for curb & gutter started August 18th and is on-going.
    • Concrete paving is complete.
    • Asphalt paving is scheduled for late September.
    • Permanent striping, concrete island construction, and swale construction is scheduled for October.
    • Utility work for the project is complete.
    • Placement of base gravels started August 3rd and is on-going.
    • Concrete work for curb & gutter started August 18th and is on-going.
    • Concrete paving is complete.
    • Asphalt paving is scheduled for late September.
    • Permanent striping, concrete island construction, and swale construction is scheduled for October.
  • September 3, 2026

    Share September 3, 2026 on Facebook Share September 3, 2026 on X (formerly Twitter) Share September 3, 2026 on Linkedin Email September 3, 2026 link
    • Work on Pierce Park Lane is mostly complete.
    • Utility work for the project is complete.
    • Placement of base gravels started August 3rd and is on-going.
    • Concrete work for curb & gutter started August 18th and is on-going.
    • Concrete paving started September 1st and will be complete by mid-September.
    • Asphalt paving is scheduled for late September.
    • Work on Pierce Park Lane is mostly complete.
    • Utility work for the project is complete.
    • Placement of base gravels started August 3rd and is on-going.
    • Concrete work for curb & gutter started August 18th and is on-going.
    • Concrete paving started September 1st and will be complete by mid-September.
    • Asphalt paving is scheduled for late September.
  • August 28, 2026

    Share August 28, 2026 on Facebook Share August 28, 2026 on X (formerly Twitter) Share August 28, 2026 on Linkedin Email August 28, 2026 link
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Westbound traffic is on the north side of State Street. Eastbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st. The work zone is currently on the south side of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Utility work for the project is complete.
    • Placement of base gravels started August 3rd and is on-going
    • Concrete work for curb & gutter started August 18th and is on-going.
    • Concrete paving is anticipated to start the week of August 31st.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Westbound traffic is on the north side of State Street. Eastbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st. The work zone is currently on the south side of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Utility work for the project is complete.
    • Placement of base gravels started August 3rd and is on-going
    • Concrete work for curb & gutter started August 18th and is on-going.
    • Concrete paving is anticipated to start the week of August 31st.
  • August 20, 2026

    Share August 20, 2026 on Facebook Share August 20, 2026 on X (formerly Twitter) Share August 20, 2026 on Linkedin Email August 20, 2026 link
    • The work zone is currently on the south side of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Asphalt removal is complete on the south side of State Street.
    • Utility work for the project is complete.
    • Contractor working on stormwater facilities.
    • Placement of base gravels started August 3rd.
    • Concrete work for curb & gutter started August 18th and is on-going.
    • Concrete paving is anticipated to start in late August or early September.
    • The work zone is currently on the south side of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Asphalt removal is complete on the south side of State Street.
    • Utility work for the project is complete.
    • Contractor working on stormwater facilities.
    • Placement of base gravels started August 3rd.
    • Concrete work for curb & gutter started August 18th and is on-going.
    • Concrete paving is anticipated to start in late August or early September.
  • August 14, 2026

    Share August 14, 2026 on Facebook Share August 14, 2026 on X (formerly Twitter) Share August 14, 2026 on Linkedin Email August 14, 2026 link
    • Eastbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st. The work zone is currently on the south side of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Asphalt removal is complete on the south side of State Street.
    • Utility work for the project is complete.
    • Contractor working on stormwater facilities.
    • Placement of base gravels started August 3rd.
    • Concrete work anticipated to start in late August.
    • Eastbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st. The work zone is currently on the south side of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Asphalt removal is complete on the south side of State Street.
    • Utility work for the project is complete.
    • Contractor working on stormwater facilities.
    • Placement of base gravels started August 3rd.
    • Concrete work anticipated to start in late August.
  • August 7, 2026

    Share August 7, 2026 on Facebook Share August 7, 2026 on X (formerly Twitter) Share August 7, 2026 on Linkedin Email August 7, 2026 link
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Westbound traffic is on the north side of State Street. Eastbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st. The work zone is currently on the south side of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Asphalt removal is complete on the south side of State Street.
    • Utility work for the project is complete.
    • Contractor working on stormwater facilities.
    • Placement of base gravels is anticipated to start the week of August 3rd
    • Concrete work anticipated to start in late August.


    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Westbound traffic is on the north side of State Street. Eastbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st. The work zone is currently on the south side of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Asphalt removal is complete on the south side of State Street.
    • Utility work for the project is complete.
    • Contractor working on stormwater facilities.
    • Placement of base gravels is anticipated to start the week of August 3rd
    • Concrete work anticipated to start in late August.


  • July 30, 2026

    Share July 30, 2026 on Facebook Share July 30, 2026 on X (formerly Twitter) Share July 30, 2026 on Linkedin Email July 30, 2026 link
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Westbound traffic is on the north side of State Street.
    • Eastbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st. The work zone is currently on the south side of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Asphalt removal is complete on the south side of State Street.
    • Utility work for the project is complete.
    • Contractor working on stormwater facilities.
    • Placement of base gravels is anticipated to start the week of August 3rd.
    • Concrete work anticipated to start in late August.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Westbound traffic is on the north side of State Street.
    • Eastbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st. The work zone is currently on the south side of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Asphalt removal is complete on the south side of State Street.
    • Utility work for the project is complete.
    • Contractor working on stormwater facilities.
    • Placement of base gravels is anticipated to start the week of August 3rd.
    • Concrete work anticipated to start in late August.
Page last updated: 02 Oct 2026, 01:55 PM