State Street and Pierce Park Lane Intersection

Share State Street and Pierce Park Lane Intersection on Facebook Share State Street and Pierce Park Lane Intersection on X (formerly Twitter) Share State Street and Pierce Park Lane Intersection on Linkedin Email State Street and Pierce Park Lane Intersection link

The Ada County Highway District (ACHD) is designing future improvements for the State Street and Pierce Park Lane Intersection. This project aims to improve safety and connectivity for all users, accommodate future traffic volumes, and incorporate ideas and concerns gathered from the public.

The improvements for State Street and Pierce Park Lane include:

  • Realigning Pierce Park Lane to improve safety and provide better line of sight for drivers
  • Widening State Street within the project limits and add medians where necessary for safety
  • Providing U-turns at multiple locations
  • Adding continuous multi-use pathways for pedestrians and cyclists
  • Adding additional crosswalk on State Street

The Ada County Highway District (ACHD) is designing future improvements for the State Street and Pierce Park Lane Intersection. This project aims to improve safety and connectivity for all users, accommodate future traffic volumes, and incorporate ideas and concerns gathered from the public.

The improvements for State Street and Pierce Park Lane include:

  • Realigning Pierce Park Lane to improve safety and provide better line of sight for drivers
  • Widening State Street within the project limits and add medians where necessary for safety
  • Providing U-turns at multiple locations
  • Adding continuous multi-use pathways for pedestrians and cyclists
  • Adding additional crosswalk on State Street
  • July 9, 2026

    Share July 9, 2026 on Facebook Share July 9, 2026 on X (formerly Twitter) Share July 9, 2026 on Linkedin Email July 9, 2026 link
    • Westbound traffic is on the north side of State Street.
    • Eastbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st.
    • The work zone is currently on the south side of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Asphalt removal has started on the south side of State Street.
    • Garden City water line installation is on-going.
    • Utility relocation work by Lumen is nearly complete.
    • Contractor working on stormwater facilities.
    • Westbound traffic is on the north side of State Street.
    • Eastbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st.
    • The work zone is currently on the south side of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Asphalt removal has started on the south side of State Street.
    • Garden City water line installation is on-going.
    • Utility relocation work by Lumen is nearly complete.
    • Contractor working on stormwater facilities.
  • July 1, 2026

    Share July 1, 2026 on Facebook Share July 1, 2026 on X (formerly Twitter) Share July 1, 2026 on Linkedin Email July 1, 2026 link
    • Westbound traffic is on the north side of State Street.
    • Eastbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st.
    • The work zone is currently on the south side of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Asphalt removal has started on the south side of State Street.
    • Garden City water line installation is on-going.
    • Utility relocation work by Lumen is nearly complete.
    • Contractor working on stormwater facilities.
    • Westbound traffic is on the north side of State Street.
    • Eastbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st.
    • The work zone is currently on the south side of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Asphalt removal has started on the south side of State Street.
    • Garden City water line installation is on-going.
    • Utility relocation work by Lumen is nearly complete.
    • Contractor working on stormwater facilities.
  • June 26, 2026

    Share June 26, 2026 on Facebook Share June 26, 2026 on X (formerly Twitter) Share June 26, 2026 on Linkedin Email June 26, 2026 link
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Westbound traffic is on the north side of State Street.
    • Eastbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st.
    • The work zone is currently on the south side of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Asphalt removal has started on the south side of State Street.
    • Garden City water line installation is on-going.
    • Utility relocation work by Lumen is nearly complete.
    • Contractor working on stormwater facilities.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Westbound traffic is on the north side of State Street.
    • Eastbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st.
    • The work zone is currently on the south side of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Asphalt removal has started on the south side of State Street.
    • Garden City water line installation is on-going.
    • Utility relocation work by Lumen is nearly complete.
    • Contractor working on stormwater facilities.
  • June 18, 2026

    Share June 18, 2026 on Facebook Share June 18, 2026 on X (formerly Twitter) Share June 18, 2026 on Linkedin Email June 18, 2026 link
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Westbound traffic is on the north side of State Street. Eastbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st.
    • The work zone is currently on the south side of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Asphalt removal has started on the south side of State Street.
    • Garden City water line installation is on-going.
    • Utility relocation work by Lumen is on-going.
    • Contractor working on stormwater facilities.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Westbound traffic is on the north side of State Street. Eastbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st.
    • The work zone is currently on the south side of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Asphalt removal has started on the south side of State Street.
    • Garden City water line installation is on-going.
    • Utility relocation work by Lumen is on-going.
    • Contractor working on stormwater facilities.
  • June 12, 2026

    Share June 12, 2026 on Facebook Share June 12, 2026 on X (formerly Twitter) Share June 12, 2026 on Linkedin Email June 12, 2026 link
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Westbound traffic is on the north side of State Street.
    • Eastbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st.
    • The work zone is currently on the south side of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Asphalt removal has started on the south side of State Street.
    • Garden City water line installation is on-going.
    • Utility relocation work by Lumen is on-going.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Westbound traffic is on the north side of State Street.
    • Eastbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st.
    • The work zone is currently on the south side of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Asphalt removal has started on the south side of State Street.
    • Garden City water line installation is on-going.
    • Utility relocation work by Lumen is on-going.
  • June 5, 2026

    Share June 5, 2026 on Facebook Share June 5, 2026 on X (formerly Twitter) Share June 5, 2026 on Linkedin Email June 5, 2026 link
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Eastbound traffic is on the south side of State Street.
    • Westbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st.
    • The work zone is currently on the south side of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Asphalt removal has started on the south side of State Street. Utility work will follow.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Eastbound traffic is on the south side of State Street.
    • Westbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st.
    • The work zone is currently on the south side of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Asphalt removal has started on the south side of State Street. Utility work will follow.
  • May 29, 2026

    Share May 29, 2026 on Facebook Share May 29, 2026 on X (formerly Twitter) Share May 29, 2026 on Linkedin Email May 29, 2026 link
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Eastbound traffic is on the south side of State Street.
    • Westbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st.
    • The work zone is currently on the south side of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Asphalt removal has started on the south side of State Street.
    • Utility work will follow.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Eastbound traffic is on the south side of State Street.
    • Westbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st.
    • The work zone is currently on the south side of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Asphalt removal has started on the south side of State Street.
    • Utility work will follow.
  • May 21, 2026

    Share May 21, 2026 on Facebook Share May 21, 2026 on X (formerly Twitter) Share May 21, 2026 on Linkedin Email May 21, 2026 link
    • Traffic calming plan has been implemented in the neighborhoods north of State Street
    • Eastbound traffic is on the south side of State Street. Westbound traffic was shifted onto the new pavement on the north side of State Street on the night of March 31st. The work zone is currently in the middle of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Asphalt and concrete paving for Phase 2 is complete.
    • The traffic shift to the 3rd and final phase was implemented on the night of May 21st.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street
    • Eastbound traffic is on the south side of State Street. Westbound traffic was shifted onto the new pavement on the north side of State Street on the night of March 31st. The work zone is currently in the middle of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Asphalt and concrete paving for Phase 2 is complete.
    • The traffic shift to the 3rd and final phase was implemented on the night of May 21st.
  • May 13, 2026

    Share May 13, 2026 on Facebook Share May 13, 2026 on X (formerly Twitter) Share May 13, 2026 on Linkedin Email May 13, 2026 link
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Eastbound traffic is on the south side of State Street. Westbound traffic was shifted onto the new pavement on the north side of State Street on the night of March 31st. The work zone is currently in the middle of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Contractor placing base gravels in the center work zone for concrete and asphalt paving.
    • Concrete paving for Phase 2 is complete.
    • Asphalt paving for Phase 2 is scheduled for the week of May 18th.
    • The traffic shift to the 3rd and final phase is scheduled for the end of May.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Eastbound traffic is on the south side of State Street. Westbound traffic was shifted onto the new pavement on the north side of State Street on the night of March 31st. The work zone is currently in the middle of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Contractor placing base gravels in the center work zone for concrete and asphalt paving.
    • Concrete paving for Phase 2 is complete.
    • Asphalt paving for Phase 2 is scheduled for the week of May 18th.
    • The traffic shift to the 3rd and final phase is scheduled for the end of May.
  • May 8, 2026

    Share May 8, 2026 on Facebook Share May 8, 2026 on X (formerly Twitter) Share May 8, 2026 on Linkedin Email May 8, 2026 link
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Eastbound traffic is on the south side of State Street.
    • Westbound traffic was shifted onto the new pavement on the north side of State Street on the night of March 31st. The work zone is currently in the middle of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Contractor placing base gravels in the center work zone for concrete and asphalt paving.
    • Concrete paving on the east leg of State Street was done April 23rd.
    • Concrete paving on the west leg of State Street is scheduled for the night of May 12th.
    • The traffic shift to the 3rd and final phase is scheduled for the end of May.
    • Traffic calming plan has been implemented in the neighborhoods north of State Street.
    • Eastbound traffic is on the south side of State Street.
    • Westbound traffic was shifted onto the new pavement on the north side of State Street on the night of March 31st. The work zone is currently in the middle of State Street.
    • Left turns have been eliminated through the work zone.
    • Work on Pierce Park Lane is mostly complete.
    • Contractor placing base gravels in the center work zone for concrete and asphalt paving.
    • Concrete paving on the east leg of State Street was done April 23rd.
    • Concrete paving on the west leg of State Street is scheduled for the night of May 12th.
    • The traffic shift to the 3rd and final phase is scheduled for the end of May.
Page last updated: 09 Jul 2026, 03:33 PM